Begin: Monday, December 19th, 2022
End: Wednesday, December 21st, 2022
Building(s) or Area(s) Affected: Gallery Way by Fine Arts Buildings
Scope: Contractor will be doing site investigations to locate underground tunnel and utilities.
- Monday 12/19 – Sawcut Asphalt
- Tuesday 12/20 – Vacuum Excavate to uncover utilities
- Wednesday 12/21 Backfill and Cover
Services Impacted: Only bicycle and pedestrian traffic will be allowed in this area. Noise can also be expected with this activity.
Work Performed By: Hoffman Construction
Contact: Denise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258