Due to stormwater drainage repairs, the courtyard surrounded by Streisinger, Huestis, Klamath, and Willamette has concrete work scheduled for 11/30 – 12/5. There will be noise and congestion associated with this work. The contractor will have the area well marked, and barricades will be in place.
Date: Time: Scope:
11/30 Starting at 6:00 pm Several holes will be drilled into the concrete
12/1 During business hours Concrete will be poured
12/1 – 12/4 During business hours Concrete curing time
12/4 Starting at 6:00 pm Concrete cutting
For questions or concerns related to this project, please contact CPFM Zone D Maintenance and Exterior Manager Kevin Farthing at 541-346-2857.