2/03/23 Powell Plaza and Agate Street Walton Crane Removal Activity and Traffic Advisory

Begin:  Friday, February 3, 2023, at 9:00 am

End:      Friday, February 3, 2023, at 5:00 pm

Building(s) or Area(s) Affected:  Powell Plaza and Agate Street

Scope:  We will be removing the tower crane from the Walton Replacement Project on the corner of Powell Plaza and Agate Street. All activities relative to the crane removal will take place within the project site fencing – nothing will be staged on Agate Street nor Powell Plaza.

Services Impacted:

  • Large trucks will be accessing the site from Agate street.  Use caution when in this area.
  • Heavier traffic can also be expected on Agate Street during this time.

Work Performed By:  Fortis Construction

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

Current construction and impacts information can be found on the UO Maps site.

20230203_crane removal (1)

1/25/23 – 1/27/23 Fine Arts Metalsmithing, Jewelry, and Woodshop Service Alley Closure

Begin:  Wednesday, January 25, 2023

End:      Friday, January 27, 2023

Building(s) or Area(s) Affected:  Woodshop and Fine Arts Metalsmithing & Jewelry buildings

Scope:  Due to tree relocation work, the service alley between the Woodshop and Fine Arts Metalsmithing & Jewelry buildings will be closed. Trees will be relocated to and planted at the Urban Farm Riverside site.

Services Impacted:  This will affect access to the service alley between Woodshop and Fine Arts Metalsmithing & Jewelry buildings – see attached logistics plan

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Tree Relocation Closure

1/19/23 East 13th Developments and Safety Plan

A traffic control plan has been approved and will be implemented in phases. The fence line has already been moved back to the north curb, allowing west bound bicycle traffic.

 

By the end of this week (1/20/23), the city plans to install water filled barriers on the portion of the street that currently has the dashed bike lane lines. This will create a protected bike/ped area on the north side of the street. This is intended to function as shared use path with both bikes and peds traveling both directions

 

On the south side of the street, the existing back-in parking will be removed to create an eastbound vehicle lane allowing LTD buses and other vehicles through. There will initially be a parallel parking area on the far south side of the street. This will convert to a pedestrian path when the Taylor’s redevelopment takes over the sidewalk on the south side.

1/17/23 – 1/19/23 JSMA Large Sculpture Installation Advisory

Begin:  Tuesday, January 17th, 2023, at 7:00 am

End:      Thursday, January 19th, 2023, at 5:00 pm

Building(s) or Area(s) Impacted:  Jordan Schnitzer Museum of Art

Scope:  A large-scale sculpture will be installed in the JSMA’s North Courtyard during the third week of January.

Services Impacted:

  • This will impact the JSMA’s parking lot (including one ADA parking spot), loading dock, security entrance, bike cage, trash collection, north courtyard, north sidewalk.
  • Crane staging and art uncrating will be located in the JSMA’s parking lot.
  • There will be limited access to the west end of Johnson Lane.

Work Performed By:  Artech, Ness Campbell, JSMA staff

ContactMiranda Callander, Jordan Schnitzer Museum of Art, 541-346-0970

To view current construction and impacts, visit UO Map.

12/19/21 – 12/21/22 Gallery Way Utility Locating Activity and Access Advisory

Begin:  Monday, December 19th, 2022

End:      Wednesday, December 21st, 2022

Building(s) or Area(s) Affected:  Gallery Way by Fine Arts Buildings

Scope:  Contractor will be doing site investigations to locate underground tunnel and utilities.

  • Monday 12/19 – Sawcut Asphalt
  • Tuesday 12/20 – Vacuum Excavate to uncover utilities
  • Wednesday 12/21 Backfill and Cover

Services Impacted:  Only bicycle and pedestrian traffic will be allowed in this area.  Noise can also be expected with this activity.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

December 2022_Gallery Way_Utility Locate Map (1)

11/28/22 – 12/16/22 Walnut Street Sidewalk Repair Advisory

Begin:  Monday, November 28th, 2022

End:      Friday, December 16th, 2022

Building(s) or Area(s) Affected:  Sidewalks on the East and West side of Walnut Street between Franklin Blvd. and East 15th Ave.

Scope:  Sections of the sidewalk will be closed for repairs, starting on the East side of Walnut, in front of the Transportation Services building, then moving down the West side, beginning at Franklin Blvd. moving south down to East 15th Ave.

Services Impacted:  Sections of the sidewalk will be closed as repairs are being made

Work Performed By:  Pacific Excavation

ContactGabe Hein, CPFM Facilities Services, 541-346-2319

Information on current construction and impacts can be found at UO Maps

11/09/22 Hendricks Hall Power Washing Noise Advisory

Begin:  Wednesday, November 9th, 2022

End:      Wednesday, November 9th, 2022

Building(s) or Area(s) Affected:  Hendricks Hall

Scope:  Power Washing on the sidewalk North West of Hendricks Hall will be taking place today

Services Impacted:  No services are expected to be impacted however, some noise from the equipment may be heard inside the building

Work Performed By:  CPFM Facilities Services Maintenance Shop

ContactGabe Hein, CPFM Facilities Services, 541-346-2319

To view current construction and impacts, visit UO Map.

11/09/22 – 1/6/23 Area between Volcanology and Columbia Hall Excavation/Utility Work Advisory

UPDATE 11/29/22:

Due to some necessary engineering changes on this project the tentative completion date is now Friday, January 6th, 2023.  The steam will still be restored as scheduled after today’s work, 11/29/22 at 3:00 pm.

UPDATE 11/22/22:
Due to piping connections needing to be made as part of the emergency steam pipe repair project, steam service will be shut down on Tuesday, November 29th, 2022 from 7:00 am until 3:00 pm in Volcanology.
There will be no heat or hot water to the building for the duration of the work.
Steam service will be restored following its completion.

 

UPDATE 11/17/22:
S-2 Contracting will be performing core drilling, adjacent to Columbia Hall, as part of the Volcanology steam pipe emergency replacement project. They will begin work prior to building occupancy, starting at 7:00 am, and will be keeping noise to a minimum, as much as possible. The noise will be intermittent at times during the course of their work, but should not be at a level that will prevent normal operations.  They are expected to complete their task by 12:00 noon.

Begin:  Wednesday, November 9th, 2022 at 7:00 am

End:      Wednesday, November 30th, 2022 at 4:00 pm Friday, January 6th, 2023 at 4:00 pm

Building(s) or Area(s) Affected:  Area between Volcanology and Columbia

Scope:  Excavation activities will be taking place for several days, between 11/9/22 and 11/16/22, generating construction noise and possible vibration. Upon completion of excavation, piping installation work will follow, with an estimated end date of 11/30/22.

Services Impacted:  Fencing will be installed around the perimeter of the work area (shown as pictured) prior to the beginning of construction activities, which will restrict travel between the Volcanology building and Columbia Hall.

Special Instructions:  Please plan to take an alternate routes of travel during this time.

Work Performed By:  S2 Industrial and Pacific Excavation

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

To view current construction and impacts. visit UO Map.

 

10/20/22 Exterior Areas of Volcanology, Columbia, and Cascade Annex Underground Utilities Work Advisory

Begin:  Thursday, October 20th, 2022, at 7:30 am

End:      Thursday, October 20th, 2022, at end of day

Building(s) or Area(s) Affected:  Lawn area and sidewalk between Volcanology and Columbia, and also by Cascade Annex West

Scope:  A contractor will be performing mapping and excavation of underground utilities between the Volcanology Building and Columbia Hall, and then adjacent to Cascade Annex West.   Work is anticipated to occur outside Volcanology from 7:30am to 10:00am, then proceed to the Cascade Annex area for the remaining time.

Services Impacted:

  • During this work, travel along the adjacent sidewalk(s) will be blocked at times.  Please consider taking other paths of travel.
  • Medium level construction noise will be occurring during this time.

Work Performed By:  Vac-X

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

To view current construction and impacts. visit UO Map.

10/19/22 – 10/22/22 ESPN College GameDay Parking Impacts

Begin:  Wednesday, October 19th, 2022

End:      Saturday, October 22nd, 2022

Scope:  ESPN’s College GameDay pregame show will be broadcast from the University of Oregon campus on October 22.

Services Impacted:

  • Parking for support vehicles will impact city of Eugene parking on Kincaid St., south of E. 13th Ave, and on E. 14th and E. 15th Avenues between Kincaid and Alder Streets beginning October 19th.
  • University permit lots will not be impacted.

Special Instructions:  Please observe posted signs.

Thank you,

James McGladrey
Assistant Director Field Operations
University of Oregon
Transportation Services
541-346-2676

10/13/22 East 13th Avenue Emergency Tree Branch Removal and Access Advisory

UPDATE:
The tree work has been completed.

 

Begin:  Thursday, October 13th, 2022 – effective immediately

End:      Thursday, October 13th, 2022 – unknown

Building(s) or Area(s) Affected:  East 13th Avenue in front of Chapman Hall

Scope:  A large overhanging branch was hit by a delivery truck and needs to be removed immediately. The area will be cordoned off.

Services Impacted:  This affects pedestrian traffic in the Street Faire area.  Work is expected to be finished within a couple of hours.

Work Performed By:  CPFM Landscape Crew

ContactRosalee Clanton, CPFM Landscape Maint Supervisor, 760-445-7302

To view current construction and impacts, visit UO Map.

9/22/22 – 9/23/22 Student Move-In parking and Traffic Impacts

As the UO welcomes new resident students to campus, Transportation Services would like to make you aware of some upcoming traffic and parking impacts that are expected the week of September 19th. To help accommodate this large move-in process, we encourage parkers to avoid parking lots around the residence halls this week.

Traffic impacts related to street closures near residence halls on 9/22 and 9/23.

  • Agate Street and portions of 13th, 15th and 17th Avenues will be restricted to Move-in traffic and vehicles on UO business.
  • All 13th Ave traffic must enter from 13th Ave and Franklin Blvd and should expect delays.
  • Permit holders will be able to access UO lots, but should expect delays
  • 13th Ave between University and Agate Streets will restricted to westbound traffic only.
  • The 13th Ave Garage will be open to permit holders
  • Lots 29A, 29D, 33, 34E, 36A and 37 will be reserved for Move in

9/22/22 Volcanology and Columbia Lawn Construction Activity Advisory 9/22/22

Begin:  Thursday, September 22, 2022 at 7:00 am

End:      Thursday, September 22, 2022 at 10:30 am

Building(s) or Area(s) Affected:  Lawn Located Between Columbia and Volcanology

Scope:  This Thursday morning, Vac-X will be performing work in the lawn area adjacent to the Volcanology building (shown in pic). Expect intermittent mid-to-high level construction noise during the course of the work.

Services Impacted:  The contractor will be parking near the sidewalk, out of the walkways, and the work zone will be roped off.

Special Instructions:  Please avoid the area while work is occurring.

Work Performed By:  Vac-X

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

To view current construction and impacts. visit UO Map.

9/21/22 – 9/23/22 Fine Arts / Gallery Walk Underground Utilities Work Advisory

UPDATED SCHEDULE:

  • 9/21 – Cancelled
  • 9/22 – Cancelled
  • 9/23 – Core Drilling of Asphalt (smaller targeted locations) and Vacuum Excavation (at removed asphalt locations)
  • 9/26 – Surveyor documentation of utility locations

 

 

BeginWednesday, September 21st, 2022 Friday, September 23rd, 2022 at 8:00 am

End:      Friday, September 23rd, 2022 Monday, September 26th, 2022 at end of day

Building(s) or Area(s) Affected:  Exterior of Fine Arts buildings in north campus – See map below

Scope:  Site investigations to locate underground utilities.

  • 9/21 at 8:00 am – Core Drilling of Asphalt (smaller targeted locations) cancelled
  • 9/22 at 7:00 am – Vacuum Excavation (at removed asphalt locations) cancelled
  • 9/23 – Surveyor documentation of utility locations  Core Drilling of Asphalt (smaller targeted locations) and Vacuum Excavation (at removed asphalt locations)
  • 9/26 – Surveyor documentation of utility locations

Services Impacted:  This affects mainly bicycle & pedestrian traffic plus will create noise when equipment is in use.

Work Performed By:  Empire Concrete Cutting, Mid State Industrial

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

To view current construction and impacts. visit UO Map.

9/06/22 – 9/10/22 Prince Lucien Campbell Hall Window Washing Advisory

Begin:  Tuesday, September 6, 2022 at 8:00 am

End:      Saturday, September 10, 2022 at 5:00 pm

Building(s) or Area(s) Affected:  Prince Lucien Campbell Hall (PLC)

Scope:  The exterior surface of the windows to entire building will be washed

Services Impacted:  No services expected to be impacted

Work Performed By:  American Cleaning Solutions

ContactKevin Farthing, CPFM Assoc. Dir Facilities Services Env., 541-359-6633

To view current construction and impacts, visit UO Map.

9/06/22 – 12/9/22 Knight Library Roofing Project Advisory

UPDATE 12/2/22:

This work is not yet complete, work will continue through next week with a projected completion date of 12/9/22

UPDATE 11/14/22:
Roofing on Knight Library should be complete by week of 11/28 based on favorable weather projections.  Construction fencing will be removed once roofing is complete and bike/pedestrian access will be restored at that time.

Thank you for your patience during this challenging project.

UPDATE 10/26/22:
Due to weather delays and unforeseen conditions, the completion date has been extended until November 30th.

 

Begin:  Tuesday, September 6th, 2022 at 6:30 am

End:      Friday, October 28th, 2022 Wednesday, November 30th Monday, November 28th, 2022 at 5:00 pm Friday, December 9th, 2022

Building(s) or Area(s) Affected:  Knight Library plus west side of Gerlinger Annex alley way between Knight Library and Cemetery.

Scope:  Roofing replacement work has begun on the middle and south sections of the building.

Services Impacted:

  • There may be some dust and odors from this work outside the building.
  • The East side of the building is closed to bikes and pedestrians.  Signs are posted to direct pedestrian and bike traffic around the North and West sides of the building.
  • Building occupants can expect to hear construction noises associated with this work which are: crane engine, banging and bumps on the 4th floor.

Work Performed By:  Preferred Construction and Umpqua Roofing

ContactBruce Budzik, CPFM Small Projects & Cap Imp Manager, 541-346-8834

To view current construction and impacts. visit UO Map.

9/01/22 Tykeson Hall Window Washing Advisory

Begin:  Wednesday, September 1, 2022 at 7:30 am

End:      Wednesday, September 1, 2022 at 5:00 pm

Building(s) or Area(s) Affected:  Tykeson Hall

Scope:  Some additional window washing will be completed

Services Impacted:  The south entrance may be blocked while windows on that side of the building are being washed

Work Performed By:  American Cleaning Solutions

ContactKevin Farthing, CPFM Assoc. Dir Facilities Services Env., 541-359-6633

 

8/26/22 – 8/28/22 Parking Lot Summer Painting Closure Advisory

Date:  Friday evening, August 26th, 2022 through Sunday, August 28th, 2022

Scope:  Summer parking lot maintenance will be performed on the weekend.

Services Impacted:

  • The lots will be closed the preceding Friday night for both Saturday and Sunday work.
  • The lots will be re-opened as soon as the paint is dry.

Parking Lot Schedule:

Saturday, August 27th, 2022

  • #33 (East of Bean)
  • #34B (N of Viv Olum Child Center)
  • #34C (E of Many Nations Longhouse/Viv Olum/Oregon Law Clinic)
  • #37 (W of Ford Alumni Center)
  • #39 (South of Agate Hall and Agate House)
  • #43 (South of Knight Law Center)
  • #44 (East Campus Graduate Village)
  • #51 (Moss Street Alley between 15th and 17th)
  • #55 (Moss Street between 15th and 17th)
  • 13th Ave Garage
  • Central Kitchen

Sunday, August 28th, 2022

  • #16A (NW of PLC)
  • #16B (West of Condon)
  • #17 (West of HEDCO)
  • #18 (West of Clinical Services)
  • #20 (NE of Beall Hall)
  • #42 (West of Computing Center)
  • #58 (Next to 1715 Franklin)
  • #59 (Romania Parking Lot)
  • Motor Pool (Franklin Blvd.)
  • 510 Oak Street
  • EC Cares (1500 W. 12th Ave.)
  • Unthank Alley

Work Performed By:  Transportation Services

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

https://map.uoregon.edu/transportation-uo

https://transportation.uoregon.edu/

8/22/22 – 9/01/22 East 15th Avenue Heavy Truck Traffic Advisory

Begin:  Monday, August 22nd, 2022

End:      Thursday, September 1st, 2022

Building(s) or Area(s) Affected:  East 15th Avenue

Scope:  Housing will be receiving many deliveries in large trucks over the next several weeks and the first to arrive will be Monday morning. A 53’ truck and 40’ Dumpster will be placed on 15th just south of LLC south and will likely remain there for the week until Thursday or Friday. (see diagrams below)

Services Impacted:  The trucks will enter campus going north on University Street and turn east on 15th (see below).

Work Performed By:  Contractors

Contact:   Lillian Moses, University Housing, 541-346-8801 and George Bleekman, CPFM Owner’s Representative, 541-346-2625

To view current construction and impacts. visit UO Map.

8/19/22 – 8/21/22 Parking Lot Summer Painting Closure Advisory

Date:  Friday evening, August 19th, 2022 through Sunday, August 21st, 2022

Scope:  Summer parking lot maintenance will be performed on the weekend.

Services Impacted:

  • The lots will be closed the preceding Friday night for both Saturday and Sunday work.
  • The lots will be re-opened as soon as the paint is dry.

Parking Lot Schedule:

  Saturday, August 20th, 2022
#2 (South of CPFM Warehouse/Shops)
#3A (North of Millrace Studios)
#3B (North of ZIRC)
#7A (West of Computing Center)
#7B (NW of McKenzie Hall)
#10 (North of Lawrence Hall)
#12A (North of Cascade Annex & Onyx)
#12B (North of Klamath & Streisinger)
#45A (Lot surrounding Transportation)
#45B (South of Transportation)
#47 (West and south of Rainier)
#60 (SE of 1900 Millrace)
Millrace Turn Around (West of Millrace Garage)

  Sunday, August 21st, 2022
13th Ave. (Agate St. to University St.)
13th Ave. (Closed portion between University St. and Kincaid St.)
Carson Loading Dock (NE corner)
15th Ave. (Onyx St. to University St.)
#23 (Between Johnson Hall and Collier House)
#25 (E of Schnitzer Museum of Art)
Johnson Hall Fire Lane (Road that ends at Schnitzer Museum)
#26 (S of Gerlinger Hall)
#27 (E of Hendricks Hall)
#28 (E of Gerlinger Hall)
#29A (S of EMU)
#29B (SW of EMU)
#29D (W of Straub)
#30 (S and E of McArthur Court and Esslinger)
#36A (E of Carson)
#36B (SW corner of University Health Services)
University St. N (E 13th Ave. to E 15th Ave.)
University St. S (E 15th Ave. to E 18th Ave.)

Work Performed By:  Transportation Services

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

https://map.uoregon.edu/transportation-uo

https://transportation.uoregon.edu/

8/16/22 – 9/30/22 Lawrence Hall Glass Curtain Replacement and Access Advisory

UPDATE:  9/21/22 – The glass curtain wall has been installed however the exterior concrete needs to be cleaned and sealed and the interior stairwell painted.  The exterior work should be completed mid week next week and the interior work by end of week, 9/30/22.

UPDATE:  8/29/22 – Due to the ongoing work to replace the window curtain wall in the West Stair Tower of Lawrence Hall, the sidewalk between Lawrence and Allen Halls will be closed 8/31/22 – 9/2/22 during working hours only

Begin:  Tuesday, August 16th, 2022

End:      Thursday, September 22nd, 2022

Building(s) or Area(s) Affected:  Lawrence Hall and sidewalk coming from E. 13th Ave.

Scope:  The glass curtain walls on the stair tower on the west side of Lawrence Hall are being replaced.  Demolition has been ongoing and replacement work will begin next Tuesday.

Services Impacted:

  • The stairwell on the west side of Lawrence Hall will be closed for the duration of the project.
  • Interior signage will be placed to show alternative egress.
  • Access through the exterior door at the base of the stairs will be largely maintained but could see temporary closures.
  • Materials will be brought to the site from 13th Street on the sidewalk along Friendly and Allen Hall.

Work Performed By:  Andersen Construction

ContactLuke Helm, CPFM Owner’s Representative, 541-346-8216

To view current construction and impacts. visit UO Map.

 

8/15/22 – 8/22/22 Sidewalk at the NW corner of Housing Phase 2 Project Closure

Begin:  Monday, August 15th, 2022

End:      Monday, August 22nd, 2022

Building(s) or Area(s) Affected:  The sidewalk between the Northwest corner of the Housing Phase 2 Project (Walton Hall) and the East side of the Living Learning Center North building

Scope:  The sidewalks and concrete flatwork associated with the project will be reconfigured

Services Impacted:

  • Pedestrian traffic will be routed north, around the closure
  • Service to Living Learning Center North will be from the south service drive

Work Performed By:  Fortis Construction

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

8/08/22 – 9/02/22 Powell Plaza Access Advisory

UPDATE:
Due to a rescheduling request from EWEB, the opening date of Powell Plaza has been changed to Saturday, September 3, 2022.

 

Begin:  August 8, 2022 at 8:00 am

End:      August 22, 2022 at 5:00 pm

Reopened:  Saturday, September 3, 2022

Building(s) or Area(s) Affected:  Powell Plaza

Scope:  We will be closing a portion of Powell Plaza to allow the Walton Replacement Project to connect to EWEB utilities.

Services Impacted:  This closure will block east/west traffic through Powell Plaza. Pedestrian traffic will be routed north around the project.

Work Performed By: Fortis Construction, Delta Construction, & EWEB

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

8/01/22 – 9/15/22 Jane Sanders Stadium Stair Access Advisory

UPDATE: The rock infill of the space between the stairs and building will take place on Thursday, 9/15/22

UPDATE:  This work is not yet complete, the stairs will be opened Monday 9/12/22 in the afternoon but will need to be closed down later in the week to infill the space between the stairs and building with rock, the date for that work is TBD at this time

Begin:  Monday, August 1st, 2022

EndFriday, September 9th, 2022 Thursday, September 15th, 2022

Building and Area Impacted: Jane Sanders Stadium

Scope:  The exterior stairs on the north side of building will be removed and replaced as part of a waterproofing project.

Services Impacted: Access to the North exterior stairs will be unavailable at this time.

Special Instructions: During this time, pedestrian traffic will be rerouted to the stairs at the Student Tennis Center.

Work Performed By:  Howard S. Wright Construction

ContactLuke Helm, CPFM Owner’s Representative, 541-346-8216

To view current construction and impacts. visit UO Map.

7/1/22 – 7/2/22 Knight Law informational advisory (windows washing)

Begin:  Friday, July 1, 2022 at 8:00 am

End:  Saturday, July 2, 2022 at 5:00 pm

Building Affected: Knight Law School

Scope: All exterior windows are being washed.

Services Impacted:  Expect temporary sidewalk and building access issues as they move around the exterior of the building.

Work Performed By:  American Cleaning Solutions

ContactKevin Farthing, CPFM Assoc. Dir Facilities Services Env., 541-359-6633

To view current construction and impacts, visit UO Map.