Willamette Hall Steam Supply/Heating Water Shutdown 6/22/21

Begin: Tuesday, June 22nd, 2021 at 7:00 am

End: Tuesday, June 22nd, 2021 at 3:00 pm

Building(s) or Area(s) Impacted:  Willamette Hall

Scope:  The steam supply/heating water will be shut down in order to replace the heating water main isolation valve in Mechanical Room #50.  This will be happening at the same time as the Hot Water shutdown to remove a backflow assembly.

Services Impacted: This will affect the steam condensate, building heat, and the domestic hot water in sinks.

Work Performed By: CPFM FS Mechanical Shop

Contact: Richard Vaughan, CPFM Facilities Services, 541-346-2319

Hayward Field Human Physiology Heating Water, Chilled Water, & Steam Shutdown 5/30/21 – 6/11/21

Begin:  Sunday, May 30th, 2021 at 7:00 am

End:      Friday, June 11th, 2021 at 3:30 pm

Building(s) or Area(s) Impacted:  Hayward Field – Human Physiology area (NW corner)

Scope:  Harvey and Price will install a bypass around the heating water flow meter, bypass around the chilled water flow meter, and bypass around the steam flow meter serving SHX-1.  Work will be performed in the mechanical room serving the Human Physiology suite in Hayward Field. Outage will not affect areas outside of Human Physiology.

Services Impacted:  This work will require shutdown to the following services: HVAC heating water system and chilled water system and the steam line feeding the domestic water heater SHX-1; domestic hot water; and heating and chilled water serving AHU-105.

Work Performed By:  Harvey & Price

ContactGene Mowery, CPFM Owner’s Representative, 541-346-5593

 

Klamath Steam Pipe Work 4/13-4/14

UPDATE 4/14/21:

The steam is back online.

 

UPDATE 4/13: While turning the steam back on a leak was discovered. Steam to Klamath and Price Science Commons will be offline overnight.

Begin:  April 13, 2021 at 4:00 am

End:      April 13, 2021 at 3:00 pm April 14, 2021

Building(s) or Area(s) Impacted: Klamath Hall and Price Science Commons

Scope: Steam pipe work to repair broken steam line

Services Impacted:  This will affect the heating, autoclave steam, and hot water to the entire building.

Special Instructions: Please turn off any equipment beforehand that may be affected by the steam outage.

Work Performed By: Utilities & Energy

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

ZIRC Heating Water Shutdown 4/14/21

Begin: Wednesday, April 14th, 2021 at 7:30 am

End: Wednesday, April 14th, 2021 at 3:00 pm

Building(s) or Area(s) Impacted: Zebrafish International Resource Center

Scope: Heating water will be shut down while repairs are made to a leaking water pipe.

Services Impacted: Building heat will be offline during this time.

Work Performed By: CPFM Facilities Mechanical Shop

Contact: Ken Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

Willamette Hall Water Shut Off 2/16 – 2/16

2/22/21 Update for Willamette Hall:

The drying phase of the Willamette Hall Room 156 water intrusion has been completed. Equipment will be removed and the cove base restored today and tomorrow. Carpets in 160, 161, & 162 will then be shampooed and the furnishings removed to their original locations.

The restoration phase of this water intrusion will be managed by CPFM. Please contact CPFM Work Control if you have any questions.

2/19/21 Update:

This is an update to the notification sent on February 18, 2021, regarding the Willamette Hall Room 156 Water Intrusion.

The mitigation equipment has been set up in Willamette Hall, including H160, 160, and 161. The equipment will run for the weekend. We will reassess on Monday morning and remove the equipment as we can.

Please feel free to contact EHS, Adam Jones, 541.346.8397 if you have any questions.

 

A water intrusion has been identified in Willamette Hall. It is currently known to be affecting rooms H160, 160, & 161.

 This intrusion occurred on Tuesday, February 16, 2021 and was the result of a clogged drain in room 156. Impacts to walls and carpets were noted in rooms 160, 161, and H160.

 The mitigation process is tasked with drying all affected materials with the ultimate goal of limiting demolition and preventing mold growth. The mitigation process is managed by Environmental Health & Safety. Mitigation efforts onsite will be conducted by CPFM. During this period, you will see fans and well dryers set up, as well as dehumidification equipment. It is important that this equipment is left running at all times to ensure that impacted building materials are dried appropriately and in a timely fashion. Mitigation is anticipated to be complete by early next week.

 The reconstruction process is tasked with returning the space to finished and operational status. The reconstruction process is managed by CPFM.

 Both mitigation and reconstruction are conducted by University staff whenever possible to save money and reduce complications associated with the work. Outside contractors are used when mitigation or reconstruction scopes exceed our available staff or equipment resources. Further information on the University’s Water Intrusion process can be found by contacting Adam Jones at asjones@uoregon.edu.

Individual departments are responsible for inventorying damaged non-building related items, such as computers, office furnishings, lab equipment, etc. The Office of Risk Management within Safety & Risk Services is available to provide guidance, inventory forms, and other information on the insurance process associated with these claims. This information can be found at https://safety.uoregon.edu/property-claims.

Finally, all future updates associated with this event will be posted to the CPFM BLOG for the event at this link: https://blogs.uoregon.edu/cpfmnotifications/2021/02/16/willamette-hal-water-shut-off-2-16-unknown/

UPDATE: The building water has been restored.

Begin:  February 16, 2021 – Immediately

End:      Unknown – An update will be sent when the water has been restored.

Building(s) or Area(s) Impacted:  Willamette Hall

Scope:  All water in Willamette Hall is unusable. There was a sewage leak and all water to the building is shut off for repairs. This includes toilets, sinks, showers, drinking fountains, etc.

Services Impacted:  All building water.

Extra Notes: An update will be sent when the water has been restored.

Special Instructions: Do not use any water in the building.

Work Performed By:  FS Mechanical Shop

Contact: Richard Vaughan, CPFM Facilities Services, 541-346-2319

Chapman and Condon Steam Shutdown 7/17/20

Begin:  Friday, July 17th, 2020 at 7:00 am

End:      Friday, July 17th, 2020 at 3:00 pm

Building(s) or Area(s) Impacted:  Chapman Hall and Condon Hall

Scope:  Due to a failed valve in the utility tunnel, the steam to both Chapman and Condon will be shut down for 8 hours to replace the valve.

Services Impacted:  The building heat and the domestic hot water will be shut off during this time.

Work Performed By:  CPFM Utilities and Energy

ContactWork Control Center, Campus Planning and Facilities Management, 346-2319

Columbia Hall Steam Shutdown 6/11/20

Begin:  Thursday, June 11th, 2020 at 7:00 am

End:      Thursday, June 11th, 2020 at 2:00 pm

Building(s) or Area(s) Impacted:  Columbia Hall

Scope:  Emergency shutdown of building steam heat due to repair of leaking main 2 inch steam pipe.  Air Handling Units SU-07, SU-08, and Heat Exchanger HEX-02, will be without heat.

Services Impacted:  This will affect the building’s heating system plus the domestic hot water in the sinks and restrooms.

Work Performed By:  CPFM Utilities and Energy

ContactWork Control Center, Campus Planning and Facilities Management, 346-2319

Willamette Hall Basement Rooms 32 and 36 Heating Water Shutdown 5/15/20

UPDATE:  Date has been moved forward to this Friday, May 15th, 2020

 

BeginWednesday, May 20th, 2020 at 7:00 am  Friday, May 15th, 2020 at 7:00 am

End:      Wednesday, May 20th, 2020 at 5:30 pm  Friday, May 15th, 2020 at 5:30 pm

Building(s) or Area(s) Impacted:  Willamette Hall Basement Rooms 32 and 36

Scope:  Hydronic piping revisions are needed on the heating water system.

Services Impacted:  Affected basement spaces may see cooler temperatures during the work.

Work Performed By:   Lease Crutcher Lewis

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Klamath Hall Utilities Shutdown 4/8/2020

Begin:  Wednesday, April 8th, 2020 at 6:00 am

End:      Wednesday, April 8th, 2020 at 4:00 pm

Building or Area Impacted:  Klamath Hall

Scope:  Final utility connections need to be made for Klamath 3rd floor South.

Services Impacted:

  • Nitrogen, Heating water, Heating Water return, Industrial Cold water, Industrial Hot Water, Hot Water Return and Chilled water will be offline to the 3rd floor south.
  • RO water will be offline to the whole building.

Work Performed By:   Lease Crutcher Lewis

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

 

LISB Steam Shutdown 4/15/2020

Begin:  Wednesday, April 15th, 2020 at 7:00 am

End:      Wednesday, April 15th, 2020 at 11:30 pm

Building or Area Impacted:  Lewis Integrative Science Building (LISB)

Scope:  Steam shutdown in the Utility Tunnel to repair a leaking 14 inch main steam valve to improve safety and stop energy losses.

Services Impacted:   Heating System, Domestic Hot Water, Steam Condensate

Work Performed By:  CPFM Utilities and Energy

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 346-2246 or CPFM Work Control Center, 346-2319

ZebraFish Stock Center 2″ Steam Pipe Shutdown 4/7/2020

Begin:  Tuesday, April 7th, 2020 at 10:00 am

End:      Tuesday, April 7th, 2020 at 10:00 pm

Building or Area Impacted:  Zebrafish International Resource Center (ZIRC)

Scope:   Twelve (12) hour shutdown required to replace an inoperable steam valve at the Central Power Station in order to safely isolate abandoned piping for demolition.

Services Impacted:  The 2 inch steam line only!  The 3 inch steam and the 3/4 inch clean steam will remain online.

Work Performed By:  CPFM Utilities and Energy

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246.  Please direct questions to Work Control at 541-346-2319.

Lawrence Hall Steam & Domestic Hot Water Shutdown 3/17

Begin:  March 17, 2020 8:00 am

End:  March 17, 2020 2:00 pm

Building(s) or Area(s) Impacted:  LAWRENCE HALL

Scope:  Heating steam will be shutdown to Lawrence Hall East. All building heat and potentially domestic hot water will be briefly shutdown to repair a leaking steam valve in the utility tunnel.

Services Impacted:  Heating Steam & Domestic Hot Water Services

Contact:  For questions or concerns, please contact Kyle Wilson 541-346-2246, rwilson2@uoregon.edu

 

Johnson Hall Building-Wide Water Shutdown 2/21/2020

Update 2/25/2020: The repairs were not able to be completed on Friday, February 21st, so the remainder of the repairs will be made tomorrow, February 26th.

Begin: Friday, February 21, 2020 at 7:00 pm Wednesday, February 26, 2020 at 7:00 pm

End: Friday, February 21, 2020 at midnight Wednesday, February 26, 2020 at 10:00 pm

Building Impacted: Johnson Hall

Scope: The plumbing issue affecting the Garden Level bathroom has been identified. A building-wide water shutdown must be enacted to make repairs.

Services Impacted: All water sources

Extra Notes: Do not use any water in the building after 7:00 pm.

Contact: Ken Straw at 541-346-5406 or kstraw@uoregon.edu

Klamath Hall Shutdowns 1/20/2020

1) Exhaust plenums and fans

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 5:00 pm

Scope:  Shutdown of the north and south exhaust plenums and fans impacting the whole building. This shutdown is to achieve the following and take advantage of the campus closure for MLK day.

  1. Disconnect ductwork for the second floor renovation area.
    2. Disconnect ductwork for phase two of level three renovation.
    3. Connect the exhaust fans to new power.

Services Impacted:  Exhaust and fume hoods throughout the building

Special InstructionsPlease close all fume hood sashes prior to the shutdown.

 

2)  Heating water

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 3:30 pm

Scope:  Shutdown of heating water that will impact level two north and level three north.  The shutdown is to isolate renovation areas on both levels and take advantage of the campus closure for MLK day.

Services Impacted:  Heating affecting Level 2 North and Level 3 North

Extra Notes:  Temporary electric heaters will be provided to warms rooms on level two.

 

3)  Steam

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 3:30 pm

Scope:  The steam shutdown is to isolate renovation areas on both levels two and three and take advantage of the campus closure for MLK day.

Services Impacted:  Shutdown of steam that will impact the full building.

 

4)  Supply fan 4

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 5:00 pm

Scope:  Shutdown of supply fan 4 that will impact the north half of Level 2 North and Level 3 North.. The shutdown is to re-sheave the fans for the renovations on both levels two and three taking advantage of the campus closure for MLK Jr. Day.

Services Impacted:  Supply air that will impact Level 2 North and Level 3 North.

ContactDenise Stewart, Owner’s Representative, 541-346-2280 or 541-335-1258

 

Lewis Integrated Science Complex Treated Steam Shutdown 12/17/19

Update 12/16/19: This work has been postponed due to a delay in the parts’ arrival. The new date is yet to be determined.

On December 17th from 7:00 am-4:00 pm the treated steam will be shutdown to Lewis Integrated Sciences to repair a leaking 14 inch steam valve in the utility tunnel. This work will impact the heating and hot water.

For questions or concerns, please contact Kyle Wilson at 541-346-2246 or rwilson2@uoregon.edu.

Klamath Hall 2nd Floor Renovation Area Heating Shutdown 12/4/19

On Wednesday morning, December 4th, from 5:00 am to 9:00 am, the second floor heating water will be shut off, likely causing a temporary reduction of temperatures.  This needs to be done to allow contractors to isolate the heating water from the 2nd floor renovation area.

Warm rooms on the floor will receive temporary electric heaters for the duration.

Work will be performed by Lease Crutcher Lewis.

For questions or concerns, please contact Denise Stewart at 541-335-1258 or dstewart@uoregon.edu.

 

Pacific Hall South Wing Labs Air and Water Shutdown 11/4/19

On Monday, November 4th, from 8:00 am to 9:00 am, the air handlers, heating water system, and chilled water system will be shutdown for approximately 30 minutes.  This will affect all south wing labs on the basement, first and second floors, south of hallway 108.

Work will be performed by Siemens.

For questions or concerns, please contact Spencer O’Neill at spencer.oneill@siemens.com.

 

Klamath Hall Steam Shutdown 10/24/19 – 10/25/19

On Thursday evening, October 24th at 7:00 pm, until Friday morning, October 25th at 7:00 am, steam (not clean steam) will be offline in order to modify steam and condensate piping for connecting to the 3rd floor renovation.  Heating water temperatures will likely be reduced until the steam is restored, at which time the temperatures will return to normal.

Temporary heaters will be supplied to controlled temperature rooms.

Work will be performed by Lease Crutcher Lewis.

For questions or concerns, please contact Denise Stewart at 541-335-1258 or dstewart@uoregon.edu.

 

 

Millrace Woodshop Emergency Treated Steam Shutdown 9/12/19

Update 9/25: The treated steam has been restored, and in turn, the heating and hot water have been restored.

 

Effective immediately, the treated steam for the Millrace Woodshop has been shut down due to a failed PRV.  The part has been ordered and will be installed upon arrival.  This will affect the heating and hot water in the building.  A notice will be sent when the steam has been restored.

For questions or concerns, please contact Work Control Center at 541-346-2319 or workcontrolcenter@uoregon.edu.

 

 

 

North Campus Steam and Hot Water Shutdown 9/4/19

On Wednesday, September 4th at 7:00 am to 5:00 pm, main steam service will be shut down while installing a shutoff valve at Knight Campus.  This shutdown will affect heating and hot water.  Building Liaisons were notified previously.

Impacted Buildings:
CPFM Warehouse 130
CPFM Building 136
Zebrafish
Fine Arts Studios
Millrace Studios
Wilkinson House
Greenhouses 109 and 110

For questions or concerns please contact:
Jeff Madsen, CPFM Design and Construction 541-346-2256
Darin Dehle, CPFM Design and Construction 541-346-2282

 

Allen Hall Heating/Hot Water Shutdown 7/12/19

On Friday, July 12th, from 6:00 am to 3:00 pm, there will be a Heating/Hot Water shutdown.  This will impact the entire building since there are no isolation valves for just the First Floor.

The shutdown is associated with the SOJC Experience Hub Remodel Project and will be initiated from the mechanical room to allow for installation of new lines.  The Heating/Hot Water is not being utilized at this time.

Work will be performed by Lease Crutcher Lewis.

If you have any questions or concerns, please contact Gene Mowery at 346-5593 or gmowery@uoregon.edu.

 

 

Willamette Hall Heating and Hot Water Shutdown 10/9 – 10/10

Building Occupants,

Due to repairs to the heating water and heating water return the hot water and heating water will be temporarily shut down on 10/9 at 9 am through 10/10 at 4 pm while crews work on the hot water system.  Facilities anticipate this will impact the SW corner of the building on all floors.

For questions or concerns please contact CPFM Facilities Services Plumber Andrew Silvius at 541-654-2926.

2/17/18: Oregon Hall 2nd and 4th East Floors Heating Water Shutdown

Building Occupant,

On Saturday, February 17th, from 6:00 am to 3:30 pm, construction activity will shut-down heating water to Oregon Hall 2nd Floor East and 4th Floor East.

The 2nd and 4th floor east areas will be without heat during the shut-down and there will be workers in the space to drain down the heating water system, recharge, and remove air from the system.

This work is required to support the renovations on the 2nd Floor to remove old hydronic piping and add isolation valves in the new 2nd Floor Mechanical Room.

Work will be performed by Fortis Construction / Hydrotemp Mechanical.

For questions or concerns about how this may impact your area, contact Patrick Mucker, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-8216.