Klamath Hall Shutdowns 1/20/2020

1) Exhaust plenums and fans

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 5:00 pm

Scope:  Shutdown of the north and south exhaust plenums and fans impacting the whole building. This shutdown is to achieve the following and take advantage of the campus closure for MLK day.

  1. Disconnect ductwork for the second floor renovation area.
    2. Disconnect ductwork for phase two of level three renovation.
    3. Connect the exhaust fans to new power.

Services Impacted:  Exhaust and fume hoods throughout the building

Special InstructionsPlease close all fume hood sashes prior to the shutdown.

 

2)  Heating water

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 3:30 pm

Scope:  Shutdown of heating water that will impact level two north and level three north.  The shutdown is to isolate renovation areas on both levels and take advantage of the campus closure for MLK day.

Services Impacted:  Heating affecting Level 2 North and Level 3 North

Extra Notes:  Temporary electric heaters will be provided to warms rooms on level two.

 

3)  Steam

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 3:30 pm

Scope:  The steam shutdown is to isolate renovation areas on both levels two and three and take advantage of the campus closure for MLK day.

Services Impacted:  Shutdown of steam that will impact the full building.

 

4)  Supply fan 4

Date:  Monday, January 20, 2020 (MLK Jr. Day) 5:00 am to 5:00 pm

Scope:  Shutdown of supply fan 4 that will impact the north half of Level 2 North and Level 3 North.. The shutdown is to re-sheave the fans for the renovations on both levels two and three taking advantage of the campus closure for MLK Jr. Day.

Services Impacted:  Supply air that will impact Level 2 North and Level 3 North.

ContactDenise Stewart, Owner’s Representative, 541-346-2280 or 541-335-1258