12/08/25 – 12/09/25 Pacific Hall Room 006 HVAC Work Advisory
Posted on

Begin:  Monday, December 8, 2025 at 8:00 am

End:      Tuesday, December 9, 2025 at 5:00 pm

Building(s) or Area(s) Affected:  Pacific Hall Room 006

Scope:  Exhaust ducting and support hangers will be installed along the ceiling.

Services Impacted:  Intermittent drilling noise and associated vibrations can be expected.  Welding of ducts may cause odors in and around the area.

Work Performed By:  FM Sheet Metal

ContactBenjamin Steingart, CPFM D&C Owner’s Representative, 541-346-7203

Current construction and impacts information can be found on the UO Maps site.

Pacific Hall room 006 on mapPacific Hall on campus map

12/15/25 – 3/25/26 LISB Room 012B Lab Remodel Advisory
Posted on

Begin:  Monday, December 15, 2025 at 7:00 am

End:      Wednesday, March 25, 2026 at 4:00 pm

Building(s) or Area(s) Affected:  Lewis Integrated Science Building Room 012B

Scope:  The Lab space will be remodeled, to include the installation of a glove box, a sputtering machine, and gas piping, as well as electrical and HVAC modifications.  Construction mobilization begins in December, demolition in early January, with major construction activities in February and March.

Services Impacted:  Construction noise and activity can be expected with occasional planned mechanical, electrical, and plumbing system shutdowns in and around room 012B.

Work Performed By:  Andersen Construction

ContactDavid Mason, CPFM Owner’s Representative, 541-346-5679

Current construction and impacts information can be found on the UO Maps site.

lewis integrated science building on the map

12/02/25 – 01/02/26 Streisinger Hall Room 276 Construction Work Advisory
Posted on

UPDATE 12/05/25:

  • Wednesday, December 10, 2025 – Saw cutting of epoxy top, noise can be expected starting at 8:00 am and ending no later than 1:00 pm
  • Thursday, December 11, 2025 – Core drilling of concrete, starting at 6:00 am and ending no later than 1:00 pm

Begin:  Tuesday, December 2, 2025, at 7:00 am

End:      Friday, January 2, 2026, at 4:00 pm

Building(s) or Area(s) Affected:  Streisinger Hall room 276

Scope:  The lab’s casework will be reconfigured in room 276.  This includes moving a sink and modifying existing casework. Demo, new finishes, plumbing and electrical will also be involved. The plumbing scope will require core drilling and a one-day plumbing shutdown that effects Streisinger Hall rooms 276, 275, 255, and 265. A separate notification will go out for the core drilling and plumbing shutdown once those are scheduled.

Services Impacted:

  • Users can expect to see contractors working in room 276 and mechanical room 190.
  • There will be periodic noise and vibrations as work continues.
  • The core drilling and plumbing shutdown will be scheduled and a separate shutdown update will be sent out for this work.

Work Performed By:  Store & Stock LLC and Brothers Plumbing

ContactGlen Macdonald, CPFM Owner’s Representative, 541-346-8201

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Streisinger Hall room 276

11/26/25 Johnson Hall Rooms 220, 221, and 222 Door Installation Advisory
Posted on

Begin:  Wednesday, November 26, 2025, at 8:00 am

End:      Wednesday, November 26, 2025, at 2:00 pm

Building(s) or Area(s) Affected:  Johnson Hall – rooms 220, 221, 222

Scope:  Permanent doors are being installed for the listed rooms.

Services Impacted:  There will be increased activity and possibly some noise.

Work Performed By:  Swinerton

ContactRenee Benoit, CPFM Owner’s Representative, 541-346-5080

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Johnson Hall rooms 220, 221, and 222

12/1/25 – 12/1/28 Portland Child Behavioral Health Building Project and Parking Access Advisory
Posted on

Begin:  Monday, December 1, 2025, at 7:00 am

End:      Friday, December 1, 2028

Building(s) or Area(s) Affected:  Centennial Hall, Mary Neils Hall, Elizabeth Hall, Weber Hall, 6441 NE 30th House, parking at NE 29th Ave. between Centennial and Holman Apts, and the East Hall’s elevator.

Scope:  Site preparation will begin for the new Child Behavioral Health Building.  Beginning Monday, 12/1, the fencing will be installed.  On the following Monday, 12/8, abatement will begin on all the structures within the fenced perimeter.  Demolition to follow abatement in Spring/ Summer of ’26. East Hall elevator to be without phone service throughout the duration. Contact facilities if you need to operate the elevator.  Updates will be sent out as the project progresses.  The Child Behavioral Health Building construction is expected to be complete in the Winter ’28/29.

Services Impacted:

  • No parking or pedestrian traffic within fencing perimeter.
  • Abatement activities mostly limited to the interior of buildings and should not affect noise levels in surrounding areas.
  • Vehicular / construction traffic to be expected.

Special Instructions:  Alternate parking is available in campus parking lots or any of the side streets, except for NE 28th Ave..

Work Performed By:  GC Skanska, Abatement by Rose City, Alpha, and PMG

ContactAnnie Karel, CPFM D&C Owner’s Representative, 541-346-8215

Current construction and impacts information can be found on the UO Maps site.

Map view of affected area for the new Child Behavioral Health Building in Portland 12-1-25 thru 12-1-28

UO CBHB Logistics_11.12.25_Phase 1 Abatement

12/01/25 – 12/19/25 Ford Alumni Center Room 209G Construction Activity
Posted on

Begin:  Monday, December 1, 2025, at 7:30 am

End:      Friday, December 19, 2025, at 3:30 pm

Building(s) or Area(s) Affected:  Ford Alumni Center – Room 209G

Scope:  CPFM crews will be refreshing the 209G kitchenette with new cabinets, countertops, faucet/sink, paint, and flooring.

Services Impacted:

  • The room will be unavailable for use by occupants for the duration of the project.
  • Occasional, light construction noises, such as drilling to remove and install cabinets, are expected.

Work Performed By:  CPFM Crew and Advanced Cabinet Designs

ContactJustin Grishkin, CPFM Construction Services Manager, 541-346-5242 or 541-510-0143

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of room 209G at the Ford Alumni Center

12/11/25 – 01/06/26 Prince Lucien Campbell Rooms 06, 07, 09, and 31 Minor Construction Work Advisory
Posted on

1st Round:  Thursday, December 11, 2025, at 7:00 am to Friday, December 12, 2025, at 3:00 pm

2nd Round:    Monday, December 22, 2025, at 7:00 am through Friday, January 6, 2026, at 3:00 pm

Building(s) or Area(s) Affected:  Prince Lucien Campbell – rooms 06, 07, 09, and 31

Scope:  Paint, electrical, and minor construction work will occur in the listed rooms.

Services Impacted:  Slight odors or noise may occur.

Work Performed By:  CPFM Crews

ContactBrianna Liberty, CPFM D&C Design Associate, 541-346-7612 or 541-556-9618

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of the location of rooms 6, 7, 9, and 31 in PLC

11/17/25 – 6/12/26 E. 13th Ave South Sidewalk Closed (Between Agate St. and the Ford Alumni Center) and Detour Advisory
Posted on

Begin:  Monday, November 17, 2025, at 7:00 am

End:      Friday, June 12, 2026, at 5:00 pm

Building(s) or Area(s) Affected:  The sidewalk on the south side of E. 13th Ave between Agate Street and the entrance to the Ford Alumni Center at Columbia Street

Scope:  The sidewalk on the south side of E. 13th Avenue from Agate St. to Columbia St. (the Ford Alumni Parking Lot) will be closed to accommodate work at the Hamilton Transformation project beginning on November 17 and lasting through June 2026. This will enhance safety by avoiding conflicts between heavy truck traffic and pedestrians at the entry and exit points.

Services Impacted:

  • Vehicular traffic flow will not be altered.
  • Pedestrians will be directed to cross to the north side of 13th Ave at the crosswalks.

Work Performed By:  Fortis Construction

ContactLuke Helm, CPFM Owner’s Representative, 541-346-8216 or 458-256-7622

Current construction and impacts information can be found on the UO Maps site.

Overhead diagram of Hamilton Transformation area showing sidewalk closure 11/17/25 thru 6/12/26

UO HWTP PH3 – TSP

11/17/25 – 11/28/25 Parking Lot 45B (South of Transportation Services) Bike Shelter Work and Partial Lot Closure Advisory
Posted on

Begin:  Monday, November 17, 2025, at 7:00 am

End:      Friday, November 28, 2025, at 4:00 pm

Building(s) or Area(s) Affected:  Parking Lot 45B (Immediately south of Transportation Services)

Scope:  A concrete slab is being poured for the creation of a new bike shelter.

Services Impacted:

  • A portion of the parking lot #45B will be closed during construction work.
  • Noise can also be expected with this activity.

Work Performed By:  Delta Sand & Gravel

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Lot 45B, just south of Transportation Services

11/10/25 Campus Wide – Project Development and Submission Timeline Reminder
Posted on

To Facilities Liaisons,

This is a reminder from our recent Facilities Liaison meeting of the Project Development guidelines and the Project Submission timelines for placing a project request.  Below are the slides showing the steps involved.

Please feel free to reach out to me if you have any questions.

Thank you.

Bruce Budzik
Email: bbbudzik@uoregon.edu
Office: 541-346-8834

Two slides showing the Project Development and Submission Timelines from the Fall 2025 Facilities Liaison meeting

10/31/25 Knight Law Center Trenching and Noise Advisory
Posted on

UPDATE:
Due to pressure issues with the hose on the vac truck, this work has been rescheduled for tomorrow, Friday October 31st from 1:00 pm to 3:00 pm.

 

BeginThursday, October 30   Friday, October 31, 2025, at 1:00 pm

End:      Thursday, October 30   Friday, October 31, 2025, at 3:00 pm

Building(s) or Area(s) Affected:  Knight Law Center

Scope:  Trench work will take place this afternoon to put down a water membrane.  This is needed to stop water leaking into Knight Law Center’s auditorium (room 184).

Services Impacted:  Loud noise can be expected during this time from the vac truck.

Work Performed By:  CPFM Crew

ContactGabe Hein, CPFM Maintenance Support Supervisor, 541-346-7563

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of the SE corner of Knight Law Center

11/07/25 University Health Services EH102 Skylight Replacement and Boom Truck Advisory
Posted on

Begin:  Friday, November 7, 2025, at 7:00 am

End:      Friday, November 7, 2025, at 12:00 noon

Building(s) or Area(s) Affected:  University Health Services – EH102 and the Loading Dock

Scope:  Culver Glass will be using a boom lift parked in the loading dock area of University Health Services for a skylight replacement in EH102.

Services Impacted:  The loading dock will not be accessible, as well as parts of hallway EH102, which will be blocked during the skylight replacement.

Work Performed By:  Culver Glass

ContactGabe Hein, CPFM Maintenance Support Supervisor, 541-346-7563

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Overhead map view showing the location of the loading dock at University Health Services

10/27/25 – 11/04/25 Riverfront Parkway Road Work and Closure Advisory
Posted on

UPDATE:
Riverfront Parkway has been reopened to traffic.

 

Begin:  Monday, October 27, 2025, at 6:00 am

End:      November 7, 2025, at 5:00 pm     Tuesday, November 4, 2025 – effective immediately

Building(s) or Area(s) Affected:  Riverfront Parkway

Scope:  The contractor must remove significant roadway material in all lanes of Riverfront Parkway. They will then rebuild and repave the roadway to meet the City of Eugene’s requirements.

Services Impacted:

  • All lanes of Riverfront Parkway will be closed.  (See map for detour route)
  • The east sidewalk will remain open for pedestrian traffic.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Overhead map view showing detour route for the Riverfront Parkway 10/27/25 - 11/07/25

10/16/25 – 10/24/25 Portland Innovation Building Compressed Air and Electrical Work Advisory
Posted on

Begin:  Thursday, October 16, 2025, at 6:00 am

End:      Friday, October 24, 2025 – unknown

Building(s) or Area(s) Affected:  Portland Innovation Building

Scope:

  • Thursday 10/16 thru Friday 10/17 – Plumbing work re new compressed air conduit will be run from east side of room at tie in over to the west side of room to new manifold/ shut off valves.
  • Thursday 10/23 thru Friday 10/24 – Electrical work re new circuit(s) at electrical panel at east wall, new power/ conduit will be run over to west side of room to new outlets.

Services Impacted:

  • Please avoid entering the work zone. Contractors will be using ladders for overhead work.
  • No compressed air for the Labs in the building during new shut off valve installation at Lab 200 – new valve will be installed by 10 AM on Thursday 10/16, service will be returned by 10 AM.
  • Soldering of copper conduit will occur on Thursday 10/16 but will be limited in duration – there will be a burning plastic smell, protection will be in place, a fire watch will be in place.

Special Instructions:

Work Performed By:  Streimer for plumbing & EC for electrical

ContactMelissa Moshofsky, CPFM Owner’s Representative, 541-346-3712

Current construction and impacts information can be found on the UO Maps site.

Diagram for the work to be done in the Portland Innovation Building room 200 10/16/25 thru 10/24/25

10/13/25 – 10/17/25 Allen Hall Concrete Work and Noise Advisory
Posted on

UPDATE:
The contractor will be doing concrete drilling to install lighting grid brackets. Expect noise and some vibration. Below are the hours of work:

  • Monday, October 13 – work 6:00 am to 10:00 am
  • Tuesday, October 14 – work 6:00 am to 8:30 am
  • Wednesday, October 15 – work 6:00 am to 10:00 am
  • Thursday, October 16 – work 6:00 am to 10:00 am
  • Friday, October 17 – work 6:00 am to 12:00 pm

 

Begin:  Monday, October 13, 2025, at 5:00 am

End:      Monday, October 13, 2025, at 9:30 am   Friday, October 17, 2025, at 12:00 noon

Building(s) or Area(s) Affected:  Allen Hall

Scope:  Contractor will be drilling concrete beams to install support brackets for lighting grid.

Services Impacted:  Anticipate noise and vibration throughout the building.

Work Performed By:  Preferred Construction

ContactRenee Benoit, CPFM Owner’s Representative, 541-346-5080

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Allen Hall

10/13/25 – 10/24/25 Riverfront Parkway Median Installation Advisory
Posted on

Begin:  Monday, October 13, 2025, at 6:00 am

End:      Friday, October 24, 2025

Building(s) or Area(s) Affected:  Riverfront Parkway

Scope:  Knight Campus Building 2 contractors must construct a new concrete median in Riverfront Parkway. Construction will occur within temporary construction barriers. See attached area of work map.

Services Impacted:  North and south vehicle traffic will be maintained on Riverfront Parkway during the work.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Map for the Riverfront Parkway Median Construction for 10-13-25 through 10-24-25

 

10/16/25 Lillis Hall Room 440A Access Advisory
Posted on

Begin:  Thursday, October 16, 2025, at 7:00 am

End:      Thursday, October 16, 2025, at 3:30 pm

Building(s) or Area(s) Affected:  Lillis Hall room 440A

Scope:  Access to room #440A will be shut down for most of the day while FM Sheet Metal replaces a failed reheat coil.

Services Impacted:  No services are expected to be impacted.

Work Performed By:  FM Sheet Metal, Inc.

ContactShaun Frasier, CPFM Plumbing and Mechanical Shop Manager, 541-346-0275

Work Control Center, Campus Planning and Facilities Management, 541-346

Overhead map view of the location of room 440A in Lillis Hall

10/13/25 – 1/09/26 Clinical Services Building Rooms 100 – 127 Remodeling Advisory
Posted on

Begin:  Monday, October 13, 2025, at 7:00 am

End:      Friday, January 9, 2026, at 4:00 pm

Building(s) or Area(s) Affected:  Clinical Services Building – Rooms 100 – 127

Scope:  The rooms listed above will be remodeled. This includes new insulation, sheetrock, painting, new flooring, new lighting, minor HVAC and plumbing modifications.

Services Impacted:

  • Occasional noise and odors typical to construction can be expected.
  • At some point, still TBD, there will need to be a water shutdown and possibly HVAC airflow.

Work Performed By:  Store and Stock LLC

ContactGlen Macdonald, CPFM Owner’s Representative, 541-346-8201

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Clinical Services rooms 100 - 127

10/03/25 UO Portland Campus Center Building
Posted on

Begin:  Friday, October 3, 2025 – unknown

End:      Friday, October 3, 2025 – unknown

Building(s) or Area(s) Affected:  UO Portland Campus Center Building

Scope:  A new dedicated breaker will be installed and power run from the electrical panel in room 212 to an outlet on the west wall in room 200.

Services Impacted:

  • Minimal disruption of power in room 200 to cut loose the outlet receiving new dedicated power.
  • Electricians will be on ladders to gain access to the ceiling cavity in order to run new wiring from the panel to the outlet – ladder and ceiling access will be in both rooms 212 and 200.
  • There may be debris from the ceiling tiles being moved, furniture may be temporarily moved out of the way for access.

Work Performed By:  EC Electric

Contact:  Melissa Moshofsky, CPFM Owner’s Representative, 541-346-3712

Current construction and impacts information can be found on the UO Maps site.

Map showing location of rooms 200 and 212 in UO Portland's Campus Center Building

10/13/25 Onyx Bridge and Cascade Annex Generator Noise Advisory
Posted on

Begin:  Monday, October 13, 2025 at 7:00 am

End:      Monday, October 13, 2025 at 5:00 pm

Building(s) or Area(s) Affected:  Onyx Bridge and Cascade Annex

Scope:  To support the Onyx Bridge EHS renovation project, a diesel generator will be placed on the sidewalk section between Cascade Annex East and Onyx Bridge.  The generator is expected to run off and on for a period of 5 or 6 hours.  A power cord covered with a cable protector will cross the adjacent sidewalk, running into Onyx Bridge.

Services Impacted:  No impediments to pedestrian traffic on the sidewalk or authorized work vehicles are expected.  Noise from the running generator can be expected in the surrounding area and nearby buildings.

Special Instructions:  Please report any Indoor Air Quality (IAQ) issues to Environmental Health and Safety.

Work Performed By:  Ryan Thomas Construction

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Onyx Bridge dock on map

9/30/25 – 10/24/25 Parking Lot #34B Access and Construction Work Advisory
Posted on

UPDATE:
A section of the side will be removed for accessible ramps.  (see diagram below)
This will shut down the red highlighted section of parking and sidewalk. The alternate route can be taken.

Additional map for the Parking Lot 34B Project from 9/30/25 - 10/24/25

 

Begin:  Tuesday, September 30, 2025, at 6:00 am

End:      Friday, October 24, 2025, at 4:00 pm

Building(s) or Area(s) Affected:  Parking Lot #34B (between Viv Olum Child Dev. Center and the Many Nations Longhouse)

Scope:  Parking Lot 34B will be closed for the addition of accessible parking spots. Project will include concrete and pavement work.

Services Impacted:  Access to Lot 34B will be completely restricted.

Work Performed By:  RiverBend Construction, Inc.

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Parking Lot 34B between Viv Olum and Many Nations Longhouse

9/13/25 – 9/14/25 Allen Hall Room 101 Floor Work Advisory
Posted on

Begin:  Saturday, September 13, 2025, at 9:00 am

End:      Sunday, September 14, 2025, at 5:00 pm

Building(s) or Area(s) Affected:  Allen Hall – room 101

Scope:  The floor in room 101 will be ground and polished over the weekend.

Services Impacted:  There will be noise and vibration throughout the building.

Work Performed By:  Preferred Construction and Bryan Matthews Concrete Finishing and Polishing

ContactRenee Benoit, CPFM Owner’s Representative, 541-346-5080

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Allen Hall room 101

9/17/25 – 9/29/25 Klamath Hall Room 245 Fume Hood Replacement and Duct Work Advisory
Posted on

UPDATE:

  • This project end date has been extended to Friday, October 10, 2025
  • Abatement contractor AAC will be onsite to perform asbestos removal above the ceiling in the same areas mentioned below

Begin:  Wednesday, September 17, 2025, at 7:00 am

End:      Monday, September 29, 2025, at 4:00 pm Friday, October, 10, 2025 at 4:00 pm

Building(s) or Area(s) Affected:  Klamath Hall – rooms 245, 249, 249A, plus hallways H207 and H208.

Scope:  The large 6-foot fume hood will be replaced in room 245. A small section of the existing exhaust ductwork will be replaced in adjacent rooms and in hall H208. Ceiling panels in hall H208 will be removed to facilitate the work.  Rooms 245, 249, and 249A are currently unoccupied.

Services Impacted:

  • Overhead work will take place in hall H208.
  • Access to room 255 will not be restricted.
  • The pathway through hall H207 may be restricted for a few hours during the work; a schedule update will be provided.
  • Please consider alternative routes around H207 during this brief period.

Work Performed By:  Harvey and Price

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Detour route on 2nd floor of Klamath Hall for fume hood work project 9/17/25 - 9/29/25

 

9/22/25 – 1/26/26 Onyx Bridge Rooms #072 – #076 Renovation Project
Posted on

UPDATE 10/22/25:
On Monday, October 27th, from 6:00 am to 8:00 am, Harvey & Price will shut off the fire sprinkler and put the fire alarm into test mode in the EHS renovation project area only. No other occupied spaces will be impacted.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations.

 

UPDATE 9/10/25:
The start date has been rescheduled to Monday, September 22, and the end date has been changed to Monday, January 26, 2026.

 

Begin:  Monday, September 15  22, 2025, at 7:00 am

End:      Monday, January 19  26, 2026, at 3:00 pm

Building(s) or Area(s) Affected:  Onyx Bridge rooms 072 – 076

Scope:  This project involves renovating and updating the existing 2,000-square-foot EH&S Waste Facilities located on the ground floor of Onyx Bridge.

Services Impacted:  Continue coordinating all hazardous waste, environmental, health and air quality issues directly with EHS, Safety, and Risk Services. Temporary offices are located on the fourth floor of Onyx Bridge, in rooms 469 and 470.

Work Performed By:  Ryan Thomas Construction

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of Onyx Bridge rooms 72 through 76

9/08/25 – 1/05/26 Portland Gymnasium Improvement Project
Posted on

Begin:  Monday, September 8, 2025, at 7:00 am

End:      Monday, January 5, 2026, at 2:00 pm

Building(s) or Area(s) Affected:  Portland Gymnasium

Scope:  The Gymnasium Improvement Project includes:

  • Basement level – upgrading vertical access from grade to basement, updating basement restrooms for all user access, adding changing rooms, shower rooms, lockers, new drinking fountain with bottle fill, updating/refreshing the weight room.
  • First floor – new drinking fountain with bottle fill, updating/refreshing the main lobby.
  • General building – new hot water heater.

Services Impacted:

  • Facilities staff located in the basement will not be able to use the stairs or areas where cordoned off for scheduled construction.
  • Users of the first-floor gym will still have access.
  • There will be no hot water in the building due to the scheduled plumbing work.
  • A portion of the east/west sidewalk at south side of building and a portion of the parking spaces at south side of building will be affected.

Work Performed By:  Howard S Wright

ContactMelissa Moshofsky, CPFM Owner’s Representative, 541-346-3712

Current construction and impacts information can be found on the UO Maps site.Drawing plans for the Portland Gymnasium Improvement Project for 9-8-25 thru 1-5-26

GymnasiumS_mm20250829
GymnasiumB_mm20250827
Gymnasium1_mm20250827