9/28/23 Huestis Hall Condensate Return Line Shutdown

UPDATE:
Due to a material delay, this shutdown will occur on Thursday, September 28.

 

BeginSeptember 26, Thursday, September 28, 2023, at 7:00 am

End:      September 26, Thursday, September 28, 2023, at 3:30 pm

Building(s) or Area(s) Affected:  Huestis Hall Basement

Scope:  As part of the Huestis Renovation project, condensate return unit (CRU-2) will be offline and removed. Existing condensate piping will be rerouted through the new CRU-1 unit.

Services Impacted:

  • The following equipment will be shut down – AHU 1&2, HWP 1&2, EF 1&2 and LEF 1&2.
  • Exhaust, fume hoods, HVAC, heating water, and steam condensate will be affected.
  • Steam Sterilizers will also be offline.

Special Instructions:  Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

map of Huestis Hall

 

9/11/23 – 9/18/23 Agate Street plus Lots 38, 39, and 43 Closure Advisory for Prefontaine Classic

Begin:  Monday, September 11, 2023

End:      Monday, September 18, 2023

Scope:  The University of Oregon is hosting the Prefontaine Classic at Hayward Field on Saturday, September 16th and Sunday, September 17th and attendance is expected to be robust.

Event impacts and related closures, as outlined below, will start on Monday, September 11th and continue through Monday, September 18th. Please anticipate an increase in traffic around campus and at the Millrace Garage during this time.

Agate Street Closures:

  • Agate Street closed from 17th Ave. to 18th Ave. beginning 9/11.
  • Agate Street closed from 15th Ave. to 18th Ave. 9/13 – 9/18.
  • Agate Street closed from 13th Ave. to 18th Ave. 9/16 – 9/17.

Campus Lot Closures

  • Lot 38 closed 9/13 – 9/17.
  • Lot 39 and 43 closed 9/16 & 9/17.

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676

Image showing Agate Street plus Lots 38, 39, and 43 affected by the Prefontaine Classic 9-11-23 thru 9-18-23

9/14/23 – 3/29/24 North Campus Concrete Truck Activity Advisory

Begin:  Thursday, September 14, 2023

End:      Friday, March 29, 2024

Building(s) or Area(s) Affected:  North Campus, Lot 3B, and Gallery Way.

Scope:  Periodically between 9/14/23 and 3/29/24 there will be concrete trucks delivering to the utility tunnel construction located between the Woodshop and Fine Arts Building C. The map below shows the truck routes in and out of the site.

Services Impacted:  On days that concrete trucks are delivering, parking stall #39 in Lot 3B will be closed for trucks to safely navigate the left hand turn off of Gallery Way.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Map of North Campus Concrete Truck Route 9-14-23 thru 3-29-24

9/07/23 Grease Trap Cleaning on West Side of Campus

Begin:  Thursday, September 7, 2023, at 8:00 am

End:      Thursday, September 7, 2023, at 4:00 pm

Scope:  Housing and Dining will have a contractor clean the grease traps in select areas on the west side of campus – see schedule below

Buildings and Schedule:

  • 8:00 am Tykeson Hall – Amy’s Corner Café
  • 9:30 am Knight Library – Café Verso #002
  • 11:00 am HEDCO – Education Station #114
  • 12:00 noon Lillis – Lillis Café
  • 1:30 pm Lawrence Hall – AAA Hearth Café #268
  • 3:00 pm Price Science Commons – Elements Café

Services Impacted:  Noise can be expected in the area, along with the possibility of encountering unpleasant odors outside the building with potential drift inside via entryways.

Work Performed By:  Roto Rooter

ContactFarrah Meade, University Housing, HCS & Work Control Manager, 541-346-4082

Current construction and impacts information can be found on the UO Maps site.

Image of buildings affected by the grease trap cleaning

9/07/23 Oregon Hall Exterior Noise Advisory

Begin:  Thursday, September 7, 2023, at 8:00 am

End:      Thursday, September 7, 2023, at 10:00 am

Building(s) or Area(s) Affected:  Along east side of Oregon Hall

Scope:  Facilities Services will be using the Vac truck to pot a new hole to replace a sign post that was broken.

Services Impacted:  Noise can be expected during this time.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Oregon Hall

10/10/23 – 10/11/23 Klamath Hall Exhaust System Shutdown

UPDATE:
The work will now be taking place on Tuesday, October 10th (North Side Exhaust Fans) and Wednesday, October 11th (South Side Exhaust Fans).  Each day’s work will take place from 7am to 4pm.

Primary building contacts have been notified, the associated effects of this work have been discussed, and accommodations are being planned for. Should you have considerations you do not feel have been addressed, please reach out to @Damon Rutherford to discuss them.

 

POSTPONED:
Based on recent findings, and pending further research, this shutdown will be rescheduled to a later date yet to be determined.

 

BeginSeptember 19, 2023, at 6:00 am  Postponed Tuesday, October 10, 2023 at 7:00 am

(daily from 7:00 am to 4:00 pm)

End:      September 20, 2023, at 6:00 pm  Postponed  Wednesday, October 11, 2023 at 4:00 pm

Building(s) or Area(s) Affected:  Klamath Hall – See attached spreadsheet for affected areas

Scope:  As part of the Klamath LEF/VFD upgrade, the mechanical contractor will be shutting down lab exhaust fans sequentially in order to upgrade the fan motors and their accessories.

Services Impacted:

  • During this work, airflow will be lessened substantially, but some will remain (in hoods, general building exhaust, etc.) as the ductwork is interconnected. However, we do not recommend using fume hoods or other equipment tied into the exhaust system during this work as appropriate airflows will not be provided.
  • Also, while the exhaust flow is lessened, there will be minor positive pressure fluctuations until the system is returned to normal operation.
    The north side fans will be shut down on 9/19/23 10/10/23, with the south side fans to follow on 9/20/23 10/11/23. Both shutdowns will be for a full days’ time, with each fan coming back online the following day, individually.

Special Instructions:  Prior to this date, please close fume hood sashes and seal containers within the fume hoods.

 Work Performed By:  Bridgeway Construction & Hermanson

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

9/12/23 – 9/14/23 Klamath Hall Exhaust Ductwork Inspection Advisory

UPDATE:
The ductwork inspection has been extended through Thursday, September 14th .

 

Begin:  Tuesday, September 12, 2023, at 8:30 am

End:      September 13, Thursday, September 14, 2023, at 4:30 pm

Building(s) or Area(s) Affected:  Klamath Hall

Scope:  Contractors will be visually inspecting exhaust ductwork throughout the building.

Services Impacted:

  • We will need access to all rooms, however, no work or disruptions will occur besides two contractors walking through the area.
  • This will affect all rooms with exhaust ductwork in the basement, ground, first, and second floors.

Work Performed By:  Air Inc.

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346-2315 or 541-525-4326

Current construction and impacts information can be found on the UO Maps site.

Image of Klamath Hall

9/21/23 – 9/23/23 Allen Hall Window Cleaning Advisory

Begin:  Thursday, September 21, 2023

End:      Saturday, September 23, 2023

Building(s) or Area(s) Affected:  Allen Hall

Scope:  The exterior windows will be cleaned and a lift will be utilized as needed.  Please close windows the night prior to the scheduled date.

Services Impacted:  Please be aware of the lift staging area.

Work Performed By:  American Cleaning Solutions

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Allen Hall

 

9/21/23 – 9/23/23 Clinical Services Building Window Cleaning Advisory

Begin:  Thursday, September 21, 2023

End:      Saturday, September 23, 2023

Building(s) or Area(s) Affected:  Clinical Services Building

Scope:  The exterior windows will be cleaned and a lift will be utilized as needed.  Please close windows the night prior to the scheduled date.

Services Impacted:  Please be aware of the lift staging area.

Work Performed By:  American Cleaning Solutions

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Clinical Services Building

9/12/23 Streisinger Hall Electrical and HVAC Systems Outage

UPDATE:
The elevator will be offline during this time.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

 

 

Begin:  Tuesday, September 12, 2023, at 7:00 am

End:      Tuesday, September 12, 2023, at 12:00 noon

Building(s) or Area(s) Affected:  Streisinger Hall

Scope:  To tie in new equipment needed to provide electrical service redundancy to Streisinger Hall, making future outages less impactful and safer for our electrical teams, a larger electrical outage is required.

Services Impacted:

Overall outage effects to consider are:

  • It will begin at 7:00 am and end at 12:00 noon (5 hour duration)
  • For the 1st hour, all power to the building will go down (110v, 208v, and 480v service)
  • After the first hour, 120v and 208v, which serves most of your lab equipment, will be live until electrical work is completed at or before 11am. All 480V service will be down for the duration of the work; this is not anticipated to have direct effects to your operations.
  • Between the 1st hour and the electrical work completion time listed above, no HVAC systems will be operating via the controls systems, but the BAS crew will be monitoring systems and making manual adjustments to reduce any risks to your operations.
  • Once the electrical work is completed, and in order to make final connections, the electrical system will go down once more for up to 1 hour.
  • Once the connections have been made all electrical service will be back in place.

We are aware that this is an inconvenience and we will do all we can to expedite the work and accommodate any needs you might have while power is limited. Thank you for your understanding and assistance as we move through this process.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

Work Performed By:  EC Electric

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

9/21/23 – 9/23/23 Lillis Complex (Anstett, Peterson, Chiles) Window Cleaning Advisory

Begin:  Thursday, September 21, 2023

End:      Saturday, September 23, 2023

Building(s) or Area(s) Affected:  Lillis Complex (Anstett, Peterson, Chiles)

Scope:  The exterior windows will be cleaned and a lift will be utilized as needed.  Please close windows the night prior to the scheduled date.

Services Impacted:  Please be aware of the lift staging area, which will move from building to building.

Work Performed By:  American Cleaning Solutions

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lillis Complex