8/15/23 – 8/17/23 Lokey Education (A&B) Emergency Heating Water Shutdown

UPDATE:
The leak has been repaired and the heating water has been restored to service.

 

Begin:  Tuesday, August 15, 2023 – effective immediately

End:      Unknown  Thursday, August 17, 2023

Building(s) or Area(s) Affected:  Lokey Education (A&B)

Scope:  The heating water has been shut down due to a leak.  An update will be sent when the repair has been completed.

Services Impacted:  Heating water will be offline during this time.

Work Performed By:  CPFM Facilities Plumbing

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lokey Ed wings A and B

8/28/23 – 9/01/23 Riverfront Parkway Road Closure

Begin:  Monday, August 28, 2023

End:      Friday, September 1, 2023

Building(s) or Area(s) Affected:  Riverfront Parkway between Millrace Drive and Franklin Boulevard

Scope:  All lanes of Riverfront Parkway will be closed to modify utilities beneath the roadway.  See the image below for detour routes.

Services Impacted:

  • Riverfront Parkway will be closed to all vehicle traffic during this time as well as the eastbound left turn lane on Franklin Blvd.
  • The east sidewalk will remain open for pedestrian traffic.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Image of detour route for Riverfront Parkway 8/28/23 - 9/1/23

8/31/23 – 9/01/23 Summer Grease Trap Cleaning Odor Advisory

UPDATE:
The work at the EMU has been rescheduled for 8:00 am on Friday, 9/1/23.

 

Begin:  Thursday, August 31, 2023

End:      Friday, September 1, 2023

Scope:  Housing and Dining will have a contractor clean the grease traps in select areas – see schedule below

Buildings and Schedule:

Thursday, August 31st

  • 9:00 am –         Central Kitchen
  • 10:00 am –       Living Learning Center
  • 11:00 am –        Global Scholars
  • 11:30 am –         Ford Alumni
  • 12:00 noon –    Carson Hall
  • 12:00 noon –    Barnhart Hall
  • 1:00 pm –          Spencer View
  • 2:00 pm –         Unthank Hall

Friday, September 1st

  • 8:00 am –         EMU
  • 9:00 am –         Tykeson Hall
  • 10:00 am –        EMU
  • 10:30 am –        Knight Library
  • 12:00 noon –    Hedco
  • 1:00 pm –          Lillis Café
  • 2:30 pm –          Lawrence Hall
  • 4:00 pm –         Elements Café  in Price Science Commons

Services Impacted:  Noise can be expected in the area, along with the possibility of encountering unpleasant odors outside the building with potential drift inside via entryways.

Work Performed By:  Roto Rooter

ContactFarrah Meade, University Housing, HCS & Work Control Manager, 541-346-4082

Current construction and impacts information can be found on the UO Maps site.

Image of locations affected by grease trap cleaning - Summer 2023

8/21/23 – 8/25/23 Vivian Olum Child Development Center Dry Rot Repair Advisory

Begin:  Monday, August 21, 2023, at 8:00 am

End:      Friday, August 25, 2023, at end of day

Building(s) or Area(s) Affected:  Vivian Olum Child Development Center

Scope:  The front entrance will be closed due to necessary dry rot repair of the roof structure above the front entry.

Services Impacted:  The front entry will be closed.  Please use a different entrance during this time.

Work Performed By:  CPFM Facilities Carpentry Crew

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Viv Olum

8/16/23 – 8/17/23 Lillis Hall North Entrance Closure Advisory

Begin:  Tuesday, August 16, 2023

End:      Thursday, August 17, 2023

Building(s) or Area(s) Affected:  Lillis Hall

Scope:  The 4th floor balcony will be pressure washed.  Water will be cascading down to the areas below, which includes the north entrance.

Services Impacted:

  • The north entrance will be closed.
  • Noise is to be expected during this time.

Special Instructions:  Please use the south entry or other entrance points.

Work Performed By:  CPFM Facilities Maintenance Support

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Lillis Complex

8/14/23 – 8/17/23 Friendly Hall Pressure Washing Advisory

Begin:  Monday, August 14, 2023

End:      Thursday, August 17, 2023

Building(s) or Area(s) Affected:  Friendly Hall

Scope:  The stairs leading to the basement will be pressure washed.

Services Impacted:

  • This will affect the basement stairwells and surrounding areas.
  • Noise is to be expected during this time.

Work Performed By:  CPFM Facilities Maintenance Support

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Friendly Hall

8/14/23 – 8/16/23 Johnson Hall North Entrance Pressure Washing

Begin:  Monday, August 14, 2023, at 7:00 am

End:      Wednesday, August 16, 2023 – until completed

Building(s) or Area(s) Affected:  Johnson Hall

Scope:  The north entrance will be pressure washed.

Services Impacted:

  • The north entrance will be closed.  Please use a different entry point.
  • Noise is to be expected during this time.

Work Performed By:  CPFM Facilities Maintenance Support

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Johnson Hall

8/22/23 Klamath Hall Lab Exhaust Fans Shutdown

Begin:  Tuesday, August 22, 2023, at 8:00 am

End:      Tuesday, August 22, 2023, at 2:00 pm

Building(s) or Area(s) Affected:  Klamath Hall

Scope:  As part of the Klamath LEF/VFD upgrade, the mechanical contractor will be shutting down lab exhaust fans sequentially in order to take field measurements required for proper equipment sizing. During this work, airflow will be lessened substantially, but some will remain (in hoods, general building exhaust, etc.) as the ductwork is interconnected. However, we do not recommend using fume hoods or other equipment tied into the exhaust system during this work as appropriate airflows will not be provided.
Also, while the exhaust flow is lessened, there will be minor positive pressure fluctuations until the system is returned to normal operation.
The fans system is split to serve the north (EF1&2) and south (EF-3&4) side of the buildings, and within the attached spreadsheet you will be able to see which rooms will be affected during the course of this (and future) shutdowns.
The listed timespan is assumed to be accurate, but we will attempt to expedite the work as much as possible.
Thank you for your understanding.

Services Impacted:  This will affect the exhaust system serving the basement, ground level, 1st, and 2nd floors.

Special Instructions:  Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.

Work Performed By:  Hermanson

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

Klamath Hall LEF Replacement Project Effects

Image of Klamath Hall

8/14/23 and 8/28/23 Lokey Education Wing C Elevator Shutdown

UPDATE:
The contractor needs to come out again to complete this work, next Monday, August 28th.  The elevator will be down for the entire day.
If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

 

Begin:  Monday, August 14, 2023 at 8:30 am plus Monday, August 28, 2023

End:      Monday, August 14, 2023 at 5:00 pm plus Monday, August 28, 2023

Building(s) or Area(s) Affected:  Lokey Education Building (Wing C – Building #41)

Scope:  Due to warranty work required for the Lokey Elevator project, the elevator will be down for the day to service the equipment.

Services Impacted:  The elevator will be offline, please use alternate means of access during this time.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By:  TK Elevator

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.

map of lokey education building C

8/15/23 Lawrence Hall Steam Heat Advisory

Begin:  Tuesday, August 15, 2023 at 8:00 am

End:      Tuesday, August 15, 2023 at 9:00 am

Building(s) or Area(s) Affected:  Lawrence Hall

Scope:  Due to the installation of a new steam pressure control valve, the steam will be turned on to set the pressure and check for leaks.  At the conclusion of testing the steam will be turned back off.

Services Impacted:  Little to no impact will be observed by building users.

Work Performed By:  Work will be performed by CPFM Utilities & Energy

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

map showing lawrence hall

8/23/23 Huestis Hall RO/DI Water Shutdown

Begin:  Wednesday, August 23, 2023, at 7:00 am

End:      Wednesday, August 23, 2023, at 11:00 am

Building(s) or Area(s) Affected:  Huestis Hall, Lokey Labs, Willamette Hall, Streisinger Hall, Onyx Bridge, Pacific Hall, Lewis Integrated Science Building, and Klamath Hall

Scope:  As part of the Huestis Renovation project, the RO system will be temporarily offline.  During this time, the RO supply may be affected in the buildings listed above.

Services Impacted:  RO water supply will be unavailable during this time.

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

map of Huestis Hall

8/16/23 Huestis Hall Basement AHU1 & 2 and Lab Exhaust Shutdown

Begin:  Wednesday, August 16, 2023, at 7:00 am

End:      Wednesday August 16, 2023, at 8:00 am

Building(s) or Area(s) Affected:  Huestis Hall Basement

Scope:  Air Handling Units 1 and 2, as well as the lab exhaust fans, will be temporarily offline for routine cleaning.

Services Impacted:  Supply and exhaust air will be offline during this time.

Work Performed By:  FM Sheetmetal and Siemens

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

map showing Huestis Hall

8/8/23 Knight Law Emergency Hot Water Shutdown

Begin:  Effective Immediately

End:      Tuesday, August 8, 2023, by end of day

Building(s) or Area(s) Affected:  Knight Law

Scope:  Due to a faulty valve the domestic hot water will be shut down to the entire building.

Services Impacted:  All sinks in labs, break rooms, and bathrooms will be without hot water until the repair can be completed.

Work Performed By:  CPFM Facilities Services Plumbing Department

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

8/09/23 Millrace 1 & 2, Fine Arts A, B, C, & Woodshop Electrical Power Shutdown

Begin:  Wednesday, August 9, 2023, at 7:00 am

End:      Wednesday, August 9, 2023, at 7:00 pm

Building(s) or Area(s) Affected:  Millrace 1, Millrace 2, Fine Arts A, Fine Arts B, Fine Arts C, & Woodshop.

Scope:  EWEB will be installing new power feeders to a new utility vault and contractors will be reconnecting buildings to new EWEB feeders.

Services Impacted:  Electrical power will be offline during this time.

Work Performed By:  EWEB and Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Image of the Fine Arts and Millrace Studio buildings that will be affected

8/9/23 Millrace Path and Gallery Walk Axis Power Pole Work Advisory

UPDATE:  EWEB has changed the schedule and will now complete this work on 8/9/23

BeginThursday, August 10, 2023 – morning Wednesday, August 9, 2023

End:      Thursday, August 10, 2023 – morning Wednesday, August 9, 2023 by 10:00 a

Building(s) or Area(s) Affected:  Area SW of Urban Farm

Scope:  On the morning of August 10th, EWEB will be removing an existing power pole near the intersection of the Millrace Path and Gallery Walk Axis that will temporarily detour bike and pedestrian traffic. (See map below)

Services Impacted:

  • This will affect access in the Millrace Path and Gallery Walk Axis area.
  • Bike and pedestrian traffic will be rerouted along Franklin Blvd. and Onyx Street.

Work Performed By:  EWEB

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

map to closure

9/06/23 Campus Wide Island Mode Testing Advisory

CPFM Utilities and Energy will perform Island Mode testing on Wednesday, September 6, 2023, between the hours of 8:00 am and 1:00 pm. Utilities and Energy staff will switch the entire campus in and out of Island Mode five times during this process (see schedule below).  Each test will begin at the top of the hour, shifting off of EWEB’s electrical grid and onto our own power generation system (called Island Mode).  At 25-minutes after the hour, we will exit out of Island Mode and return back to EWEB’s power source.  As a result, short duration power outages may occur at any time throughout the testing period. The electrical distribution system redundancy and resiliencies depend upon the properly functioning power generation system and island mode capabilities.

Thank you for your patience as we resolve our issues related to exiting island mode with our emergency equipment. On-site personnel will include the original electrical engineer that designed the system, ASCO technicians and a new company that brings more resiliency and oversight for Utilities and Energy.

  • 8:00 am – 8:05 am  Execute 1st island mode test.
  • 8:25 am – 8:30 am  Exit island mode.
  • 9:00 am – 9:05 am  Execute 2nd island mode test.
  • 9:25 am – 9:30 am  Exit island mode.
  • 10:00 am – 10:05 am  Execute 3rd island mode test.
  • 10:25 am – 10:30am  Exit island mode.
  • 11:00 am – 11:05 am  Execute 4th island mode test.
  • 11:25 am – 11:30 am  Exit island mode.
  • 12:00 noon – 12:05 pm  Execute 5th island mode test.
  • 12:25 pm – 12:30 pm  Exit island mode.
  • 12:30 pm – 1:00 pm  Monitor campus electrical systems, insure systems normal and all testing complete.
  • 1:00 pm Testing complete and an all-clear message sent from Work Control Center.

Network Impacts: When any building’s power is off, its wired and wireless networks will also stop working. During the Sept. 6 power testing: 

 Expect intermittent campuswide network outages. 

  • Localized lingering network outages may occur if network devices fail. If so, Information Services staff will post notices on the IT Service Status website. Recovery will begin after CPFM issues its all-clear message and could take a day or longer 

Information Services (IS) offers the following guidance about protecting electronic devices from power surges during the Sept. 6 power testing. 

 Before the Testing – Turn Off Electronics 

Most electronic devices that plug into wall sockets should be shut down and unplugged before the power testing begins. Such devices can be damaged by the power surge when the power is turned back on. Even surge protectors don’t guarantee that sensitive devices will be preserved. 

 Who needs to take action depends on the type and location of the equipment: 

  •  Individual computers and devices: 
    • Shut down and unplug desktop computer, dock, printer, and other sensitive electronics. 
    • Unplug laptops. 
  • Other classrooms and non-classroom areas: 
    • Sensitive devices include research equipment, multifunction copiers, videoconference systems, digital display panels, microwaves, and Crestron control systems and other AV equipment. 
    • Preparations may be handled by the User Support Services team in Information Services, by departmental IT staff where applicable, or by other departmental staff, following existing patterns of support. 
    • IS User Support Services will contact departments they support to coordinate specifics. 

 After Testing Ends – Restart Electronic Devices

  • IS staff will turn on AV equipment in general pool and joint-controlled classrooms, prioritizing spaces with active classes. That process could take several days. To request faster service restoration for specific classrooms, please submit a ticket through the classroom technology support page in the UO Service Portal. 
  • IS staff also plan to turn on other equipment that they shut down before the testing. However, please feel free to restart such devices once the testing is complete. 

Work Performed By:  CPFM Utilities & Energy 

Contacts:

Locations not included in the testing:  
Oak Street
E. Broadway
942 Olive
1600 Millrace
1715 Franklin
1900 Millrace
Alder Building
Autzen Stadium
Baker Downtown Center (975 High St.)
Casanova Athletics
EC Cares Buildings (1500 W. 12th Ave plus modules)
Fleet Services (Glenwood) (3233 Franklin Blvd.)
Hatfield-Dowlin Complex
KWAX (75 Centennial Loop)
McMorran House (2315 McMorran Drive)
Moshofsky Sports
PeaceHealth North (677 12th Ave.)
PK Park
Rainier (1244 Walnut St.)
Randy and Susie Pape Complex
Romania Warehouse (2020 Franklin Blvd.)
South A Warehouse (1199 South A St., Spfld.)
Thompson University Center (720 E. 13th Ave.)
Transportation Services (1401 Walnut St.)
Tree Tops (2237 Spring Blvd.)
UOPD East Station (2141 E. 15th Ave.)

Current construction and impacts information can be found on the UO Maps site.

Image of map of campus

POSTPONED – Pacific Hall Building Automation System Firmware Updates

UPDATE:
Due to unforeseen Siemens staffing shortages, the firmware updates will be postponed until further notice.

 

BeginMonday, August 21, 2023, at 7:30 am  POSTPONED

End:      Monday, August 21, 2023, at 9:30 am  POSTPONED

Building(s) or Area(s) Affected:  Pacific Hall’s Bradshaw Lab and NE corner Suites 304, 305 and 306.

Scope:  To maintain reliability of the Building Automation System controllers, Siemens will be performing firmware updates on Panels PXCC118, PXCC119, and PXCC120.

Services Impacted:

  • This will affect the heating and HVAC air supply.
  • Expect a two-hour system outage with no remote access to the BAS system in the Bradshaw Lab and NE corner Suites 304, 305 and 306.

Work Performed By:  Siemens

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of rooms affected in Pacific Hall

8/01/23 – 8/7/23 – Fenton Hall Passenger Elevator Emergency Shutdown

UPDATE:  The elevator has been repaired and returned to service.

Begin:  Tuesday, August 1, 2023 – effective immediately

End:  Unknown Monday, August 7, 2023

Building Impacted:  Fenton Hall

Scope:  The passenger elevator is down for repairs.  Parts have been ordered but due to supply chain shortages, it may take a while for them to arrive.

Services Impacted:  The elevator will be offline during this time.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By: Otis

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of Fenton Hall Passenger Elevator