6/09/25 – 6/17/25 EMU Esports, Duck Nest, and Fishbowl Restrooms Closure
Posted on

UPDATE:  These additional spaces and equipment will also be out of service while this work is being done:

  • First Floor
    • Bathroom next to the freight elevator(Room 151)
    • Back kitchen, back hallway dishwasher and ice machine(Rooms 157 & H151)
  • Mezzanine
    • Men’s and Women’s restrooms(Rooms M143A & M138A)
    • Custodial closet(Room M144)
    • All-gender restroom(Room M148)
    • Breakroom(Room M146)
    • Mud Room(Room M154)
  • Second Floor
    • Servery and custodial closet(Rooms 241 & 241A)
  • Third Floor
    • Greenroom bathroom(Room 350C)

Begin:  Monday, June 9, 2025 at 7:00 am

End:      Tuesday, June 17, 2025 at 5:00 pm

Building(s) or Area(s) Affected:  Erb Memorial Union Rooms 040, 041, 159, and 160

Scope:

Due to a plumbing project:

  • Esports Room 040 and Duck Nest Room 041 will be closed
  • Fishbowl Restrooms 159 and 160 will be offline

Services Impacted:

  • There will be no disruptions to fraternity and sorority spaces, the computer lab, or freight elevator access.
  • Odor may be present due to drain line removal, but the following steps will be taken to minimize this.
    • HVAC will be optimized to extract odors.
    • Portable filtration equipment will be deployed.

Work Performed By:  Twin Rivers Plumbing

ContactChad Wells, EMU Building Superintendent, 541-346-0692

Current construction and impacts information can be found on the UO Maps site.

EMU First floor map showing 040 and 041EMU First floor map showing restrooms 159 and 160

6/09/25 – 6/10/25 1776 Millrace HVAC Shutdown
Posted on

Begin:  Monday, June 9, 2025 at 8:30 am

End:      Tuesday, June 10, 2025 at 5:00 pm

Building(s) or Area(s) Affected:  1776 Millrace Drive

Scope:  Contractor will be on site to service the HVAC system.

Services Impacted:  Heating and Cooling will be shut down periodically while this work is being done.

Work Performed By:  Comfort Flow Heating Co.

Contact:  Lydia Fitzpatrick, CPFM Campus Planning, Real Estate and Leasing Coordinator, 541-346-3804

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

1776 Millrace on map

6/17/25 – 8/12/25 Old Campus Quad Summer Construction Projects Advisory
Posted on

Begin:  Tuesday, June 17, 2025 at 7:00 am

End:      Tuesday, August 12, 2025 at 5:00 pm

Building(s) or Area(s) Affected:  Areas in and around Villard Hall, University Hall, Lawrence Hall, Pacific Hall, Friendly Hall, and Collier House

Scope:  There are four construction projects happening in areas surrounding the Old Campus Quad area.

Services Impacted:  This will affect vehicle and bicycle parking, as well as maintenance service and pedestrian travel routes.  This notice is meant to be an overview of the impact of these projects on campus.  More detailed notices pertinent to each specific project will be sent out separately if they have not been already.  An illustration of these impacts has been provided on the map below and on the attachment to this notice.

Work Performed By:  Various contractors

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Old Campus Quad impacts illustrated on the map

5/27/25 – 5/28/25 Hendricks Hall Construction Noise Advisory
Posted on

Begin:  Tuesday, May 27, 2025

End:      Wednesday, May 28, 2025

Building(s) or Area(s) Affected:  Hendricks Hall

Scope:  Some light construction work will be performed in Hendricks Hall room 105.

Services Impacted:  No services are expected to be impacted but some minor noise may be observed in and around the area.

Work Performed By:  CPFM Crews

ContactTad Lueck, CPFM FS Structure and Support Manager, 541-346-2273

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Hendricks Hall on the map

5/30/25 Pacific Hall Air Handling Unit Shutdown
Posted on

Begin:  Friday, May 30, 2025 at 8:00 am

End:      Friday, May 30, 2025 at 1:00 pm

Building(s) or Area(s) Affected:  Pacific Hall, Cascade Hall, Cascade Annex

Scope:  AHU-1 in Pacific Hall will be shutdown so that the air intake area in the alley east of the building can be painted.

Services Impacted:  Fresh air intake to Pacific will decrease while this work is being done.  Paint smell may be observed in Pacific, Cascade, and Cascade Annex.

Work Performed By:  CPFM Paint Department

ContactShaun Frasier, CPFM Plumbing and Mechanical Shop Manager, 541-346-0275

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Pacific Hall on map

4/24/25 Huestis Hall Emergency Vacuum Pump Shutdown
Posted on

Begin:  Thursday, April 24, 2025 effective immediately

End:      Thursday, April 24, 2025

Building(s) or Area(s) Affected:  Huestis Hall

Scope:  The vacuum pump for Huestis Hall has been shutdown for an emergency repair which is expected to take a few hours to complete.  Another notice will be sent out when the work is done.

Services Impacted: Vacuum service to the whole building will be down until the repair is complete.

Work Performed By:  CPFM Mechanical Shop

ContactShaun Frasier, CPFM Plumbing and Mechanical Shop Manager, 541-346-0275

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Huestis Hall on map

4/23/25 – 4/25/25 Straub Hall Green Landscaping Advisory
Posted on

Begin:  Wednesday, April 23, 2025 at 7:00 am

End:      Friday, April 25, 2025 at 4:00 pm

Building(s) or Area(s) Affected:  Straub Green, Straub Hall, Esslinger Hall, Student Recreation Center, EMU

Scope:  Landscaping and grounds work will be taking place in the Straub Green area to the west of Straub Hall.

Services Impacted:  No services are expected to be impacted, but noise may be observed in nearby buildings.  Sidewalks surrounding the area may be blocked off as needed throughout the course of the work.

Work Performed By:  Rexius

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Straub Green on map

3/18/25 Peterson Hall Emergency Heating Shutdown
Posted on

UPDATE:  The heating system at Peterson has been repaired and brought back online.

 

Begin:  Tuesday, March 18, 2025 – effective immediately

End:      unknown Tuesday, March 18, 2025

Building(s) or Area(s) Affected:  Peterson Hall

Scope:  A power outage caused by a chilled water leak damaged the Variable Frequency Drive that powers the heating system water pump.  A replacement part has been ordered and will be installed as soon as possible.  An update will be sent out when heating has been restored to the building.

Services Impacted:  Heating will be unavailable to all Peterson Hall until repairs can be made.

Work Performed By:  CPFM BAS Crew

ContactStacy Breaux, CPFM FS Building Automation Systems Field Supervisor, 541-346-2304

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

peterson hall on the map

3/18/25 Anstett Hall Emergency Heating and Cooling Shutdown
Posted on

UPDATE:  The heating system in Anstett has been repaired and brought back online.

 

Begin:  Tuesday, March 18, 2025 – effective immediately

End:      unknown

Building(s) or Area(s) Affected:  Anstett Hall

Scope:  Due to a chilled water leak the Variable Frequency Drives(VFD) that control the heating and cooling water pumps that serve Anstett Hall have shorted out.  The heating water system will be brought back online this morning with the one spare VFD we have on hand and a replacement has been ordered to replace the drive to return the cooling pumps to service as soon as possible.  An update will be sent out once the heating is restored.

Services Impacted:  Heating and cooling will be unavailable to all Anstett Hall until repairs can be made.

Work Performed By:  CPFM BAS Crew

ContactStacy Breaux, CPFM FS Building Automation Systems Field Supervisor, 541-346-2304

Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

anstett hall on map

3/3/25 Cascade Hall Emergency Heating Water Shutdown
Posted on

UPDATE:  The emergency work has been completed and the heating water restored to the building.

Begin:  Monday, March 3, 2025, effective immediately

End:      Monday, March 3, 2025, at 12:00 pm

Building(s) or Area(s) Affected:  Cascade Hall

Scope:  Heating water will be shutdown to the building for emergency repairs on Air Handler Unit #4.

Services Impacted:  Heating to the entire building will be off for the duration of this work.

Work Performed By:  CPFM Mechanical Shop

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

cascade hall on map

2/27/25 – 2/28/25 1700 Millrace Pressure Washing Noise Advisory
Posted on

UPDATE:  This work has been extended through this week and will now be completed Friday, March 7, 2025.

Begin:  Thursday, February 27, 2025 at 7:00 am

End:      Friday, February 28, 2025 at 3:00 pm Friday, March 7, 2025 at 3:00 pm

Building(s) or Area(s) Affected:  1700 Millrace Exterior

Scope:  Pressure washing of the exterior entrances and sidewalks of the building will take place.

Services Impacted:  No services will be impacted but noise can be expected throughout the course of the work.

Work Performed By:  CPFM Maintenance Support

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

1700 Millrace on map

3/4/25 Lillis Hall Chilled Water Shutdown
Posted on

Begin:  Tuesday, March 4, 2025 at 8:00 am

End:      Tuesday, March 4, 2025 at 2:00 pm

Building(s) or Area(s) Affected:  Lillis Hall

Scope:  Due to a leak on a chilled water pipe in the tunnel, chilled water will be shutdown to the building to make repairs.

Services Impacted:  Minimal impact is expected due to the current weather making chilled water for air conditioning unnecessary.

Work Performed By:  CPFM Utilities and Energy

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

lillis hall on map

3/10/25 – 3/11/25 Klamath Hall and ZIRC Clean Steam Shutdown
Posted on

Begin:  Monday, March 10, 2025 at 7:00 am

End:      Tuesday, March 11, 2025 at 3:00 pm

Building(s) or Area(s) Affected:  Klamath Hall and Zebrafish International Resource Center

Scope:  Due to annual maintenance on the Central Power Station clean steam generator, clean steam will not be available.  Treated 60 psi steam will be provided in place of the clean steam during the maintenance.

Services Impacted:  Minimal impact is expected as only a couple of machines are still served by CPS clean steam.

Work Performed By:  CPFM Utilities and Energy

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

klamath hall on mapzirc on map

2/26/25 – Unknown Lawrence Hall Emergency Elevator Shutdown
Posted on

UPDATE:  The elevator has been repaired and returned to service.

Begin:  Wednesday, February 26, 2025 – effective immediately

End:      Friday, February 28, 2025

Building(s) or Area(s) Affected:  Lawrence Hall

Scope:  The elevator is down for an emergency repair.  An update will be sent when it has been restored to service.

Services Impacted:  The elevator will be offline during this time.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By:  Otis

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

lawrence hall on map

March 2025 Campus Air Handling Unit Preventative Maintenance Schedule
Posted on

Begin:  March 1, 2025

End:     March 31, 2025

Building(s) or Area(s) Impacted:

  • Frohnmayer Music
  • HEDCO
  • Clinical Services
  • Lokey Education A & B
  • Lokey Education C
  • Education Annex
  • Berwick Hall
  • 510 Oak Street
  • UOPD East Station

Scope:  AHU preventative maintenance work is scheduled to be performed, over the course of the month, for the buildings listed above.

Services Impacted:  No services are expected to be impacted.

Work Performed By:  CPFM Preventative Maintenance Crew or Contractor

Contact:  Work Control Center, Campus Planning and Facilities Management, 541-346-2319.

Current construction and impacts information can be found on the UO Maps site.

campus map

2/11/25 – 2/12/25 Onyx Bridge Liquid Nitrogen Tank Work and Sidewalk Detour Advisory
Posted on

UPDATE:
The sidewalk in front of Onyx Bridge room 092 (east side of building) will be restricted for pedestrians. There is an alternate route around the loading dock.

Aerial view of detour at the Onyx Bridge loading dock for 2/11/25 - 2/12/25

 

UPDATE:
This work has been rescheduled for Tuesday, February 11, 2025, at 1:00 7:00 am through Wednesday, February 12, 2025, at 4:00 pm.

 

BeginFriday, February 7, 2025, at 7:00 am    Tuesday, February 11, 2025, at 1:00 7:00 am

End:      Friday, February 7, 2025, at 4:00 pm   Wednesday, February 12, 2025, at 4:00 pm

Building(s) or Area(s) Affected:  Onyx Bridge room 092

Scope:  A contractor will be onsite to install electric vaporization for the existing LN2 tank at Onyx Bridge.

Services Impacted:  No interruption to services is expected.

Work Performed By:  US Cryogenics Inc.

ContactWaymon Banks, CPFM Owner’s Representative, 541-346-0196

Current construction and impacts information can be found on the UO Maps site.

Onyx Bridge on the map

1/29/25 – 1/30/25 Frohnmayer Music Building Emergency AHU-1 Shutdown
Posted on

UPDATE:  The repair has now been completed and all systems in the building are now back online.

UPDATE:  An electrical panel will be shutdown today 1/30/25 at 1:00 pm for 2 hours to replace a breaker for AHU-1.  The panel also serves AHU-2 which will shutdown heating to the following additional spaces for 2 hours. Rooms 105, 109, 118,120, 203, 205, 207, Vestibule V220, and Lobby L120.

Begin:  Wednesday, January 29, 2025

End:      unknown Thursday, January 30, 2025

Building(s) or Area(s) Affected:  Frohnmayer Music Building

Scope:  Due to a yet to be determined cause, a reset on the freeze stat for AHU-1 continues to cause an electrical breaker to trip.  As a result, that Air Handling Unit will be shutdown until the issue can be resolved.

Services Impacted:  All rooms on the first and second floors represented on the maps below are served by AHU-1 and can expect the heat to be affected by this shutdown.  An update will be sent out when the equipment is back online.

Work Performed By:  CPFM Facilities Services

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

1/27/25 Klamath Hall Emergency Industrial Hot Water Shutdown
Posted on

Begin:  Monday, January 27, 2025

End:      Monday, January 27, 2025 at 12:00 pm

Building(s) or Area(s) Affected:  Klamath Hall

Scope:  Industrial hot water will be shutdown to replace a faulty safety valve.

Services Impacted:  There will be no hot water to labs or custodial closets, domestic hot water will be unaffected.

Work Performed By:  CPFM Plumbing Shop

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

klamath hall on the map

1/23/25 – Unknown Agate Hall Theatre Room 111 Emergency Heating Fan Shutdown
Posted on

Begin:  Thursday, January 23, 2025

End:      Unknown

Building(s) or Area(s) Affected:  Agate Hall Room 111

Scope:  The 100-year-old fan that feeds heated air into room 111 has failed and is unrepairable.  The fan is currently being removed to get measurements so that a replacement can be ordered or another solution can be devised.

Services Impacted:  There will be no direct heating to this room until a solution is put into place.

Work Performed By:  CPFM Mechanical Shop and Design and Construction

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Agate Hall on map

1/24/25-1/28/25 1700 Millrace Drive Odor Advisory
Posted on

Begin:  Friday, January 24, 2025 at 7:30 am

End:      Tuesday, January 28, 2025 at 3:00 pm

Building(s) or Area(s) Affected:  1700 Millrace Drive

Scope:  All paper towel and soap dispensers in the building restrooms and break rooms are being replaced with new ones.  A citrus based adhesive remover will be used to remove dispensers that are attached to mirrors as needed.

Services Impacted:  No services will be impacted but odor from the adhesive remover may be observed throughout the building.

Work Performed By:  CPFM Maintenance Support

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

1700 Millrace Drive on map

1/27/25 – 1/28/25 Agate Hall Concrete Removal Noise Advisory
Posted on

Begin:  Monday, January 27, 2025 at 7:30 am

End:      Tuesday, January 28, 2025 at 3:00 pm

Building(s) or Area(s) Affected:  Agate Hall

Scope: Jack hammering and vacuuming with a vacuum truck to remove subgrade material and investigate the cause of a steam leak in room 111F will take place in the alley to the east of Agate Hall.

Services Impacted:  No impact to services is expected but noise associated with the work can be expected throughout the building.

Work Performed By:  CPFM Facilities Services Maintenance Support and Mechanical Shops

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

agate hall on map

1/27/25 Lawrence Hall Emergency Elevator Shutdown
Posted on

Begin:  Monday, January 27, 2025 at 9:00 am

End:      Monday, January 27, 2025 at 1:00 pm

Building(s) or Area(s) Affected:  Lawrence Hall

Scope:  Otis Elevator will be replacing a failing valve on the elevator at the North end of the building near the dock entrance.

Services Impacted:  The elevator will be unavailable for use during this time.

Special Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By:  Otis Elevator

Contact:  Work Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

lawrence hall on map

1/27/25 – 1/31/25 Knight Library Restrooms 126 & 127 Shutdown
Posted on

Begin:  Monday, January 27, 2025 at 8:00 am

End:      Friday, January 31, 2025 at 5:00 pm

Building(s) or Area(s) Affected:  Knight Library Restrooms 126 and 127, Vestibules V126 and V127

Scope:  Existing toilet partitions will be demolished and new partitions installed.

Services Impacted:  Both restrooms and the vestibules leading into them will be closed for the duration of this work.

Work Performed By:  Change Commercial

Contact:  Nathan Chaffee, nchaffee@uoregon.edu, 541-346-2279

Current construction and impacts information can be found on the UO Maps site.

knight library on mapknight library interior map

12/9/24 CPFM/FASS Fuel Island Inspection Advisory
Posted on

Begin:  Monday, December 9, 2024 at 8:00 am

End:      Monday, December 9, 2024 at 11:00 am

Building(s) or Area(s) Affected:  CPFM/FASS Fuel Island

Scope:  The DEQ will be doing the annual underground storage tank inspection.

Services Impacted:  The fuel island will be periodically unavailable during this time.

Work Performed By:  Department of Environmental Quality

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

fuel island on the map

Posted in Gas
12/18/24 Miller Theatre Complex Steam Shutdown
Posted on

Begin:  Wednesday, December 18, 2024 at 7:00 am

End:      Wednesday, December 18, 2024 at 1:00 pm

Building(s) or Area(s) Affected:  Miller Theatre Complex

Scope:  Steam will be shut off while a new steam valve is installed to feed Villard Hall.

Services Impacted:  Heat to the entire building will be off for the duration of this work.  This has been scheduled during winter break to reduce interruptions to building users.

Work Performed By:  Alliant Systems

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Current construction and impacts information can be found on the UO Maps site.

Miller Theatre Complex on map