UPDATE 12/18/25:
All plumbing has been turned back on except for the DI water system. This will be turned back on tomorrow morning at 7:00 am.
Begin: Thursday, December 18, 2025, at 7:00 am
End: Thursday, December 18, 2025, at 4:00 pm / Friday, December 19, 2025, at 7:00 am
Building(s) or Area(s) Affected: Streisinger Hall – rooms 255, 255A, 255B, 255C, 255D, 265, 265A, 265B, 265C, 273, 275, 275A, 276, 276B, 276C, 276D, 276E
Scope: The plumbing for domestic cold and hot water, RO water, gas, and compressed air, will be shut down as construction work continues on room 276.
Services Impacted: No water, gas, or compressed air will be available in the highlighted rooms – see below
Work Performed By: Brothers Plumbing
Contact: Glen Macdonald, CPFM Owner’s Representative, 541-346-8201
Current construction and impacts information can be found on the UO Maps site.