Notice: Huestis Natural Gas, Lab Air, RO Water, Potable Water and Heating Water Shutdown 2/9 and 2/10 from 6 pm – 7 am

Due to the installation of new isolation valves located in the SE building riser, the below services will be interrupted in Huestis for two consecutive nights of shut-downs from 6PM-7AM on February 9, 2017, and February 10, 2017.  Utilities will be turned on during the day.  Two nights have been scheduled for the work, although the contractors may be able to complete the work in 1 night depending on progress and condition of old lines.

Natural Gas – Building Wide

Laboratory Air – Building Wide

Reverse Osmosis Water – Building Wide

Potable Cold Water – Building Wide

Potable Hot Water – Building Wide

Heating Water – 3rd floor only

This is part of the third-floor lab renovations project.  This work was scheduled overnight to limit the impact to building occupants.