REVISED UPDATE:
After additional discussions, we are returning to the original schedule with Straub Hall testing to take place first thing Wednesday morning and Pacific Hall testing to take place on Thursday.
UPDATE:
Due to a scheduling conflict, Pacific Hall has been moved to Wednesday and Straub Hall has been switched to Thursday.
Begin: Monday, July 14, 2025, at 7:00 am
End: Thursday, July 17, 2025, at 4:00 pm
Building(s) or Area(s) Affected: Erb Memorial Union (EMU), Student Rec Center (SRC), Straub Hall, Willamette Hall, Knight Library, and Pacific Hall
Scope: Traction full load tests will be performed on 2-3 elevators per day. (See schedule below.)
Services Impacted: Each unit will be out of service during the test for approximately 2-3 hours. Only one elevator will be taken offline at a time.
Special Instructions: If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.
Monday, July 14, 2025
Erb Memorial Union – #1 (Middle) and #2 (North)
Tuesday, July 15, 2025
Student Rec Center – #3 (By climbing wall) and #4 (South)
Wednesday, July 16, 2025
Straub Hall – #2 (South)
Willamette Hall – only 1 elevator
Thursday, July 17, 2025
Knight Library – #4 (South)
Pacific Hall – only 1 elevator
Work Performed By: CPFM Facilities and Otis Elevator
Contact: Rob Berg, CPFM Electrical Supervisor, 541-346-2313
Work Control Center, Campus Planning and Facilities Management, 541-346-2319