Knight Library #364-#366 Renovation 6/17/19 – 8/31/19

Beginning June 17th, and continuing until the end of August, the general contractor, Preferred Construction, and their subs will be doing renovation work in rooms 364-366 in the Knight Library.  This will involve asbestos abatement, minor demo and framing, drywall, duct work, electrical, carpet and paint.  Users can expect to hear normal and occasional construction noises such as hammering and drilling, and may smell a water-based latex, non-toxic paint, during the painting portion.  Users will see the contractor, their subs and UO personnel entering/exiting the building with tools and materials during normal business hours.

During abatement (6/18-6/20), CPFM staff will turn off the HVAC system, which might affect areas outside the construction zone on the third floor.

No other utility disruptions or shutoffs are expected at this time, but if there are any more, then an additional notice will be distributed.

If there are any issues or concerns, please contact Theo Davis, the CPFM project manager, at 541-346-1012, or tdavis1@uoregon.edu.

CPFM Building 130 Construction Activities 9/10 – 9/14

Abatement for the future Work Control Center area in CPFM Building 130 will begin on Monday 9/10, and it should be complete by 9/14. The contractors will be using two parking spaces north of the building, one for a dumpster, and one for their equipment van. Please expect increased activity and noise in this area.

For questions or concerns please contact CPFM Design and Construction Project Manager Tim Allenbaugh at 541-346-8214.

Bean Hall Project Road Closures July 19, 2018

Campus Community,

There are two street closures for the Bean Hall Project on July 19th.

The first is a closure of 15th street between Bean and Global Scholars Hall from 6 AM to 8 AM. We will shut down the street with flaggers to detour traffic, set up the crane and lift the rooftop units.

The second closure will be Columbia Street between Hamilton Hall and the Alumni Center. We will be closing the parking spots in lot 37 as part of the closure. This closure will be from 6 AM – 3 PM. Access to the Columbia Garage will not be affected.

For questions or concerns please contact CPFM Design and Construction Project Manager George Bleekman 541-346-2625.

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/07/General-Sheet-Metal-Bean-Hall-Crane-Pick-Site-Plan-1-1reluog.pdf” download=”all” viewer=”google” ]

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/07/Crane-Laydown-Aerial-View-2-212zc7g.pdf” download=”all” viewer=”google” ]

3/19 – 3/23: McKenzie Suite 275 Abatement

Building Occupants of McKenzie Suite 275:

Beginning Monday, March 19th at 4:00 pm until Friday, March 23rd, a contractor will be performing asbestos abatement in Suite 275.  The contractor has requested that all the HVAC supply/returns in the suite to be shut off so they can cover up the vents with plastic.

Work will begin at approximately 4:00 pm and they will work in the evening.  We expect them to finish by Friday but it could end sooner, TBD.
Abatement work will be performed by Rose City.

For questions or concerns about how this may impact your area, contact Theo Davis, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-1012.

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2018/03/Mckenzie-275-Floor-Plan-area-of-work-5-1xpx2r3.pdf” download=”all” viewer=”google” ]

12/6 – 12/8: Evening Hallway Closure Huestis 2nd Floor beginning 12/6 at 7:00 pm

Building Occupants,

As part of the Huestis Hall 2nd Floor projects, the corridor/hallway flooring on the 2nd floor will be replaced. The activity will include asbestos abatement. Abatement work is tentatively scheduled to occur Wednesday, December 6 – Friday, December 8, 2017.

Preparation for this work will start at 7:00 pm on 12/6. Sections of the corridor will be inaccessible the evenings of Wednesday 12/6 through Friday 12/8. The hallways will be open starting at 5:00 am each morning.

Special Instructions:

If you need custodial closet access, elevator access or north stairwell access please contact the project manager Colin Brennan directly at (541) 346-8242 or (541) 654-2972.

For questions or concerns about this project, contact Colin Brennan, CPFM Design and Construction at (541) 346-8242 or (541) 654-2972.

8/14 – 9/6: Straub, Earl, LLC and Carson Steam Shutdown Related to Tunnel Abatement Project

Building Occupants,

Due to the 2017 Tunnel Abatement and Insulation Project all steam will be temporarily shut down that services Straub, Earl, LLC and Carson  from August 14 – September 9, 2017.

(Click on map to view full size)

For questions on how this may impact your services please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317or Mo Soleimani CPFM Utilities and Energy Maintenance Supervisor 541-346-2213.

8/14 – 9/11: Chapman, Condon and PLC Steam Shutdown Related to Tunnel Abatement Project

Building Occupants,

Due to the 2017 Tunnel Abatement and Insulation Project all steam will be temporarily shut down that services Chapman, Condon and PLC from August 14 – September 11, 2017.

For questions on how this may impact your services please contact Jana Gerow CPFM Design and Construction Owners Representative 541-346-8317or Mo Soleimani CPFM Utilities and Energy Maintenance Supervisor 541-346-2213.

8/7/17 update: Oregon Hall Renovations

Oregon Hall Renovations- Project Status Update

  1. Next week Abatement activities will be completed on First Floor west (Tuesday 8/8) and Fortis Construction will begin construction activities (Wednesday 8/9)
  2. Fortis Construction will be setting up a construction trailer in Lot 14 (north of Oregon Hall) and installing site fencing to create a materials staging area (beginning Monday 8/7)
  3. 2nd Floor- Workspace 220; We have removed the systems furniture and have abatement activities scheduled for the night of Wednesday 8/9. Work will begin at 6 PM and be complete by 6 AM. The plastic containment area will need to be left in place Thursday during air testing. There will be some after hours duct work Monday-Wednesday to support the work. On Saturday 8/12 Fortis will construct walls for the new mechanical room to isolate construction areas from work areas. All loud activities will be scheduled after-hours.
  4. 3rd Floor- Office 342 and Women’s Restroom 341; Abatement activities are scheduled in these areas the night of Thursday 8/10. Work will begin at 6 PM and be complete by 6 AM. The plastic containment area will need to be left in place Friday during air testing. The Women’s Restroom will be closed indefinitely beginning at 6 PM Thursday 8/10 since we are installing roof-top equipment above. We will try to re-open the restroom around construction activities. On Saturday 8/19 Fortis will construct walls for the new electrical room to isolate the construction activities from work areas. All loud activities will be scheduled after-hours.

Information provided by UO Safety and Risk Services:

Asbestos abatement is completed with a controlled environment. Unaffected surfaces are covered with thick plastic sheeting and thoroughly sealed, any penetrations are sealed, and the work area entry is protected by a two flap air lock. Air is constantly removed from the work area through use of a machine called an air filtration unit (AFU). This machine draws air from the work area, forces it through a series of filters, and then exhausts it to the exterior of the building. The final filter is HEPA, which removes 99.97% of particulate measuring .3 microns and smaller. The work area is under negative pressure, meaning that air can’t escape except through our AFU.

You may notice plastic sheeting walls with asbestos signage on them. These are to notify you of a potential hazard inside of the enclosure and are required by OSHA and LRAPA regulations. There also will be a long plastic exhaust duct. This duct carries the filtered exhaust air out of the containment and exhausts it to the building exterior. All of these controls are designed and proven to keep the potential hazard inside of the containment and away from you. If you have any questions or concerns, please contact Environmental Health & Safety at 6-3192.

Please contact me or Adam Jones with any questions.

Patrick Mucker
Owner’s Representative
Campus Planning and Facilities Management
University of Oregon
541-346-8216 office
541-517-2497 cell

 

 

7/31/17-8/2/17: Onyx Bridge Demolition and Abatement Work Continues

Building Occupants,

On the evenings of Monday, July  31st and Tuesday, August 1st, from 5:00 pm until the following mornings at 5:00 am, demolition & abatement work needs to continue at Onyx Bridge.  This will affect the 2nd-floor rooms 270, 270A, 271, 272, 278, 279, 280, 281 and 282.

No utilities will be impacted, but there will be noise and some vibration from demolition activities.

Work will be performed by an abatement contractor.

For questions or concerns about how this may impact your area, contact Denise Stewart, Campus Planning and Facilities Management (CPFM) Design and Construction at 346-2280.

 

07/25 – 7/28: Onyx Bridge 2nd Floor Noise and Vibration Due to Construction Activities

Additional Information from Safety and Risk Services

PMG will begin asbestos abatement and demolition work in the second floor of Onyx Bridge tonight, including rooms 270, 270A, 271, 272 (west portion), 278, 279, 280, 281, and 282.  This work will be done from 5 pm to 5 am to avoid disruption to building occupants.  The hallway will not be blocked for this work.  The contractor will be removing casework, fume hoods, non-asbestos flooring, and a few CMU walls.

Please let me know if you have any questions or concerns.

__________________________________

Mike Eldredge Asbestos Program Manager
http://ehs.uoregon.edu
Safety and Risk Services | University of Oregon
5224 University of Oregon | Eugene, OR 97403-5224
Office: 541.346.2908| Fax: 541.346.7010
cellular 541.206.4488|
______________________________________

Building Occupants,

Due to construction, Onyx Bridge building occupants should expect noise and some vibration from demolition activities July 25 – 28, 2017.  Rooms impacted are: 270, 270A, 271, 272, 278, 279, 280, 281 and 282.  Work will occur between 5 pm and 5 am for the remainder of the week.  There will be no impacts to utility services.  A progress update will be sent on Friday, July 28th if work needs to continue into next week.

For questions or concerns, please contact CPFM Design and Construction Owners Representative Denise Stewart at 541-346-2280.

Extended & New Date and Time: Pacific Hall Corridor Abatement

Update: 1/9/17

Due to continued inclement weather and to limit the impact to building occupants the contractor will begin set up January 10th after 2 pm and has scheduled the ceiling cleaning and hallway closures for off hours, after 5 pm on January 10th and 11th.

If you have question or concerns, please contact Jen Miley, Research Manager, Capital Planning and Facilities Management at  541-346-1530 office 317-956-0640 cell.

_______________________________________________________________________________________________________________________

Update: 1/6/17

This work has been extended into next week.  Starting Monday morning the contractor will be onsite working above the corridor ceilings.  The work will begin in the basement and then move to the first and second floors.  This work will include removal of minor asbestos insulation debris.  The areas below the ceilings will not be an abatement area, but building occupants should temporarily avoid the corridors during this cleanup work.  Signage will be at each end of the hallway that will indicate the temporary closure.  Only one hallway will be closed at a time.

If you have question or concerns, please contact Jen Miley, Research Manager, Capital Planning and Facilities Management at  541-346-1530 office 317-956-0640 cell.

_________________________________________________________________________________________________________________________

Building Occupants,

In preparation for the renovation of the laboratories on the basement, first and the second floor of the south wing of Pacific Hall, we will be closing the south portion of each of these the hallways for a week at a time, to perform floor tile removal (see attached plans for affected areas).

The schedule for this work is:

Basement: December 19th- 23rd

Second Floor: December 26th – 30th

First Floor: January 2nd – 6th

Except for access to occupied spaces within the project area, these hallways will be closed to traffic for this time.

In the weeks following the abatement work, the project will erect semi-permanent partitions, blocking these corridors (except for access to occupied spaces) to begin demolition and construction.

This project will run through 2017 and into the beginning of 2018. Access from Pacific Hall to Onyx Bridge will remain open through the construction project.

If you have question or concerns, please contact Jen Miley, Research Manager

[embeddoc url=”https://blogs.uoregon.edu/cpfmnotifications/files/2017/01/Pacific-Hall-Flooring-Revised-28zv9dx.pdf” download=”all” viewer=”google”]