This message is to notify the campus community of the start of construction for the Knight Campus Building 2 project. Building 2 will be a four-story research building located north of Building 1 and west of Riverfront Parkway.
The project will include a sky bridge connection to Building 1 and a utility tunnel connection to existing campus utility systems. Sky bridge- and utility tunnel- specific information will be shared at a later date, closer to the beginning of those work activities.
Start of the project is Monday, December 12, 2022, and project complete is scheduled for August 29, 2025.
Closures will include parking Lot 4, a portion of the Millrace Path between Gallery Way and Riverfront Parkway, as well as the gravel access road between Gallery Way and Riverfront Parkway.
Riverfront Parkway will have revised traffic patterns but maintain 2 lanes with shared bicycle traffic.
Contact Design and Construction, Owner Representative, Denise Stewart at dstewart@uoregon.edu or 541-346-2280 with any project-related questions.
Work will be performed by Hoffman Construction.
To view current construction and impacts, see the UO Map.
UO_Knight Campus Phase 2_Bike Path Detour_Final
UO_Knight Campus Phase 2_Site Logistics_Winter Break_Final