UPDATE 7/29/25:
To accommodate an addition to the project’s excavation work, construction fencing will be adjusted on 8/4/25, as shown on the attached site layout, to create an alternative pedestrian route. This fencing configuration, and associated pathway, will remain in place until 8/15/25. The fencing will then return to its prior layout, on 8/16/25.

2nd UPDATE 7/18/25:
The concrete delivery mentioned below has been delayed, due to subcontractor schedule changes, and will now be taking place between 8:00 am and 10:00 am instead of 5:00 am to 7:00 am.
UPDATE 7/18/25:
The blue bins for paper, block Styrofoam, and food scraps are located behind Pacific Hall near the end of the fire lane. The dumpsters for garbage and cardboard recycling are still situated by the front of Columbia Hall as mentioned previously.

UPDATE 7/17/25:
On Monday, July 21st, from 5:00 am to 7:00 am, the contractor will be performing concrete pours, and as part of that, expect several concrete trucks and additional equipment moving around and through the worksite and adjacent portions of the lot.
Due to the early timing, this is not expected to provide much, if any, disturbance. Only anticipated difficulty could be limited vehicular movement withing the parking lot itself, during the work, possibly causing minor delays.

UPDATE:
The dumpsters for garbage and recycling have been moved from east side of Pacific Hall to the west side of Columbia Hall for the duration of this project.

Begin: Monday, June 30, 2025, at 7:00 am
End: Monday, September 8, 2025, at 5:00 pm
Building(s) or Area(s) Affected: Entirety of parking lot 12A’s west side spaces and associated ADA spaces, Lawrence Hall west entry, and adjacent east side walking path (as shown in site logistics plan)
Scope: Beginning 6/30/25, in order to install an electrical vault towards bettering Campus electrical service and safety, Andersen Construction and Pacific Excavation will be performing excavation work, and repaving, within the west side of parking lot 12A, adjacent to Lawrence Hall’s east side entry. Please see attached logistics plan for a more detailed perspective. Thank you for your understanding as we carry out this work.
Services Impacted:
- During this work there will be times of consistent, as well as intermittent, construction noise, particularly during the excavation phase of the project. There will be some vibration during the associated earthwork compaction.
- Some odor will also be present during the paving portion, and it will be mitigated as much as possible.
- There will also be a short-term electrical shutdown, to be schedule at a time that will produce as much limited interruption and inconvenience as possible. Once the timing of that task is defined, this notice will be updated for your awareness.
Work Performed By: Pacific Excavation & Andersen Construction
Contact: Damon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285
Current construction and impacts information can be found on the UO Maps site.