UPDATE:
The work did not take place as planned. The installation has been rescheduled for Wednesday, August 17th.
Begin: Monday, July 18th, 2022 Wednesday, August 17th, 2022
End: Tuesday, July 19th, 2022 Wednesday, August 17th, 2022
Building(s) or Area(s) Affected:
- Willamette Hall Rm. 272
- LISB Rm. 204B and Rm. B017
- Klamath Hall Rm. B61
- Lokey Labs Rm. 53A
Scope:
- As part of the process chilled water project in Willamette there are five locations that are getting end of line flow control valves installed
- Initial assessment and measurement requiring 20 minutes in each location
- Installation of bypass piping requiring 20 minutes in each location
- Fabrication of bypass piping will take place outside, no soldering will occur inside the buildings
Services Impacted: Each of these locations already have isolation valves from previous projects so no shutdowns are required and no impacts to the system will occur
Work Performed By: S2 Industrial
Contact: Kevin Waldrop, CPFM Facilities Engineer, Design & Construction, 541-346-2315