8/17/22 Willamette Hall, LISB, Klamath Hall, Lokey Labs – End of Line Flow Control Valve Installation

UPDATE:
The work did not take place as planned.  The installation has been rescheduled for Wednesday, August 17th.

 

BeginMonday, July 18th, 2022 Wednesday, August 17th, 2022

End:      Tuesday, July 19th, 2022 Wednesday, August 17th, 2022

Building(s) or Area(s) Affected:

  • Willamette Hall Rm. 272
  • LISB Rm. 204B and Rm. B017
  • Klamath Hall Rm. B61
  • Lokey Labs Rm. 53A

Scope:

  • As part of the process chilled water project in Willamette there are five locations that are getting end of line flow control valves installed
  • Initial assessment and measurement requiring 20 minutes in each location
  • Installation of bypass piping requiring 20 minutes in each location
  • Fabrication of bypass piping will take place outside, no soldering will occur inside the buildings

Services Impacted:  Each of these locations already have isolation valves from previous projects so no shutdowns are required and no impacts to the system will occur

Work Performed By:  S2 Industrial

ContactKevin Waldrop, CPFM Facilities Engineer, Design & Construction, 541-346-2315

7/8/22 Gerlinger Hall Water Meter Replacement Notice

Begin:  Friday, July 8, 2022 at 6:00 am

End:      Friday, July 8, 2022 at 8:00 am

Building(s) or Area(s) Affected:  South East Gerlinger parking strip. The flow meter will be tested after install. Water from testing will be directed to the street gutter and is not a concern.

Scope:  Due to a failed water meter, EWEB will be replacing the meter for Gerlinger Hall early Friday morning. There will not be any water outage. The meter bypass water pipeline will be active during the work.

Services Impacted:  There will be little to no impact to campus.

Work Performed By:  EWEB

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246

7/7/22 East of Agate Hall, Columbia Alley Closure Advisory

Begin:  July 7, 2022 at TBD

End:     July 7, 2022 at TBD

Scope:  Fill and replace gravel on Columbia Alley.

Building(s) or Area(s) Affected: East of Agate Hall, Columbia Alley from 17th Ave. through 19th Ave.

Services Impacted:  Users can expect no access to Columbia Alley.

Work Performed By: CPFM Landscape

Contact:  Rosalee Clanton, Landscape Maintenance Supervisor, CPFM, 541-346-2319

7/1/22 – 7/31/22 Campus Air Handling Unit Preventative Maintenance Schedule for July 2022

Begin:  July 1st, 2022

End:     July 31th, 2022

Building(s) or Area(s) Impacted:

  • Thompson University Center
  • Prince Lucien Campbell Hall
  • EC Cares Modular Classroom
  • EC Cares Modular Westmoreland
  • EC Cares Main Office
  • Condon Hall

Scope:  Preventative Maintenance work will be performed, over the course of the month, for the buildings listed above.

Services Impacted:  No services are expected to be impacted.

Work Performed By:  CPFM Preventative Maintenance Crew or Contractor

ContactKyle Harshbarger, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

6/15/22 Huestis Hall Clean Steam Shutdown

Begin:  June 15, 2022 at 7:30 am

End:      June 15, 2022 at 3:30 pm

Building(s) or Area(s) Affected:  Huestis Hall

Scope:  As part of the Huestis Renovation Project, building clean steam will be shutdown and unavailable.

Services Impacted:  Autoclave Steam, Steam Condensate

Work Performed By:  Mortenson Construction and JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

6/13/22 – 6/14/22 Streisinger and Lokey Labs Steam Shutdown

UPDATE:
This ended up taking place later on a different notification. (8/24/22 – 8/25/22)

 

POSTPONED:

Due to unusually cold weather and negative impacts to critical research, the steam shutdown and condensate pump repairs are postponed.

BeginJune 13, 2022 at 3:00 pm TBD

End:      June 14, 2022 at 3:00 pm TBD

Building(s) or Area(s) Impacted:  Streisinger and Lokey Labs

Scope:  Due to failed and leaking condensate return pumps, the steam will be shutdown to replace both pumps.

Services Impacted:  Building heating will be off for 24 hours.

Work Performed By:  CPFM Utilities and Energy

Contact:  Kyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246

6/6/22 – 6/7/22 East 15th sidewalk closure between SRC and Hayward

Begin:  June 6, 2022 at 7:00 am

End:      June 7, 2022 at 6:00 pm

Building(s) or Area(s) Affected:  East 15th between SRC and Hayward Field

Scope:  Sidewalk closure for the installation of medium voltage cable between the Student Rec Center and Hayward Field

Services Impacted:  The sidewalk on the north side of the Athletic Turf Field between Hayward Field and the Student Rec Center will be closed

Work Performed By:  LR Brabham

ContactDale Stadler, CPFM D&C Project Electrical Engineer, 541-346-8251

5/31/22 – Unknown – Baker Downtown Center Restrooms Shutdown

UPDATE 6/30/22:
The restrooms are to remain shut down until further notice. The issue is ongoing, there is no known time when they will be reopened.

 

Begin:  May 31st, 2022

End:      Unknown

Building(s) or Area(s) Impacted:  Baker Downtown Center – Restrooms 201A and 202A

Scope:  The two restrooms are closed by order of the City of Eugene until the sewer line to the street can be repaired by the City

Services Impacted:  Restroom facilities in Rooms 201A and 202A only

Special Instructions:  Use Restrooms down the Hall, Rooms 209 and 211

Work Performed By:  City of Eugene

ContactRon Warren, CPFM Facilities Plumbing, 541-346-2319

8/9/22 – 10/31/22 CPFM Back Forty Area Access Advisory

UPDATE:  8/9/22

  • Although the shotcrete and pre-stressing activities have ended work within and around the Thermal Energy Storage Tank Project Area continues
  • Travel paths through the area should be avoided until completion of the overall project work

UPDATE:  7/14/22

  • This work has been extended until 8/4/22

BeginMay 23, 2022 Tuesday, August 9th, 2022

End:      July 31, 2022   August 4, 2022​​ Monday, October 31st, 2022

Area Impacted:  CPFM Back Forty Area to the West of Utilities and Energy

Scope:  Beginning the week of 5/23/22 there will be intermittent shotcrete applications as well as significant pre-tensioning activities in the Back Forty area.

Services Impacted:

  • During shotcrete applications no parking will be allowed along the perimeter surrounding the central plant on the south, north or west sides (see attached picture).
  • During the pre-tensioning work parking and transit will remain closed on the Central Plants west side, and no workers or transit will be allowed within the work area (see attached picture) due to high level safety concerns.
  • The project team is communicating with affected work groups towards enabling work to continue with as limited interruption as possible.

Additional Notes: Additional notices/schedules will be posted prior to the start of these activities, but please keep this upcoming work in mind for your future planning.

Work Performed By:  DN Tanks

Contact:  For questions or concerns, please contact Damon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

5/12/22 – 5/25/22 ZIRC Chilled Water, Treated Steam, and Untreated Steam Shutdown

UPDATE 5/20: Additional shutdowns will be required. Times and dates are still being reviewed by all that will be involved. Activities will be completed next week on Monday 5/23 and/or Wednesday 5/25. The project team will communicate with building users once times are confirmed.

Begin:  May 12, 2022 at 06:00 am

End:      May 19, 2022 May 25, 2022 at 05:00 pm

Building(s) or Area(s) Impacted:  Zebrafish International Resource Center

Scope:  Utility meter installation will require that we shut down the chilled water, treated steam, and untreated steam to the building.

Services Impacted:

  • The chilled water and treated steam will be restored same day on the 12th.
  • The untreated steam to the building will be off until May 19th to allow time to complete work associated with that system.

Work Performed By:  Fortis Construction

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

8/09/22 Baker Downtown Center Chilled Water Shutdown Notice

Begin:  Tuesday, August 9th, 2022 at 7:00 am

End:      Tuesday, August 9th, 2022 at 4:00 pm

Building(s) or Area(s) Affected:  Baker Downtown Center, Rooms 100 – 140

Scope:  The chilled water system that serves the air handling units for the south side of the building will be shut down

Services Impacted:   The affected areas will not have air conditioning during this time

Work Performed By:  FM Sheet Metal

Contact: Kyle Harshbarger, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

7/26/22 – 8/8/22 Living Learning Center Service Drive Closure

Begin:  Tuesday, July 26th, 2022 at 7:00 am

End:      Monday, August 8th, 2022 at 5:00 pm

Building(s) or Area(s) Affected:  Living Learning Center Service Drive

Scope:  We will be closing part of the service drive to the east of LLC to finish civil work related to the replacement of Walton Hall.  Service to the buildings during this time will be from the north, and pedestrians routed to the north and south.

Work Performed By:  Fortis/Delta Construction

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625