Begin: Monday, September 8, 2025, at 7:00 am
End: Monday, January 5, 2026, at 2:00 pm
Building(s) or Area(s) Affected: Portland Gymnasium
Scope: The Gymnasium Improvement Project includes:
- Basement level – upgrading vertical access from grade to basement, updating basement restrooms for all user access, adding changing rooms, shower rooms, lockers, new drinking fountain with bottle fill, updating/refreshing the weight room.
- First floor – new drinking fountain with bottle fill, updating/refreshing the main lobby.
- General building – new hot water heater.
Services Impacted:
- Facilities staff located in the basement will not be able to use the stairs or areas where cordoned off for scheduled construction.
- Users of the first-floor gym will still have access.
- There will be no hot water in the building due to the scheduled plumbing work.
- A portion of the east/west sidewalk at south side of building and a portion of the parking spaces at south side of building will be affected.
Work Performed By: Howard S Wright
Contact: Melissa Moshofsky, CPFM Owner’s Representative, 541-346-3712
Current construction and impacts information can be found on the UO Maps site.
GymnasiumS_mm20250829
GymnasiumB_mm20250827
Gymnasium1_mm20250827