UPDATE:
The coming rain has postponed the start of this paving project to Friday, September 13th. The duration is now expected to be only one day
Begin: Thursday, September 12 Friday, September 13, 2024
End: Friday, September 13, 2024
Building(s) or Area(s) Affected: Gallery Way, Urban Farm, Millrace Studios, Fine Arts Studios & Woodshop
Scope: New asphalt paving placement to repair surfaces at new tunnel construction.
Services Impacted:
- Closure of Gallery Way and alleyway between Fine Arts C & Woodshop.
- There will be odor during asphalt work. Keep operable windows closed in buildings adjacent to the work.
- Pedestrian and bicycle traffic will be rerouted during this time.
Work Performed By: Hoffman Construction
Contact: Denise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258
Current construction and impacts information can be found on the UO Maps site.