9/13/24 Gallery Way Paving and Odor Advisory

UPDATE:
The coming rain has postponed the start of this paving project to Friday, September 13th.  The duration is now expected to be only one day

 

BeginThursday, September 12     Friday, September 13, 2024

End:      Friday, September 13, 2024

Building(s) or Area(s) Affected:  Gallery Way, Urban Farm, Millrace Studios, Fine Arts Studios & Woodshop

Scope:  New asphalt paving placement to repair surfaces at new tunnel construction.

Services Impacted:

  • Closure of Gallery Way and alleyway between Fine Arts C & Woodshop.
  • There will be odor during asphalt work. Keep operable windows closed in buildings adjacent to the work.
  • Pedestrian and bicycle traffic will be rerouted during this time.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.

Overhead map view of paving project location on Gallery Way 9/12/24 - 9/13/24