8/18/22 Allen Hall Transformer Testing Electrical Shutdown

Begin: Thursday, August 18th, 2022 at 8:00 am

End:     Thursday, August 18th, 2022 till 6:00 pm

Building Impacted:  Allen Hall

Scope:

  • Due to Data center required utility transformer testing the power will be shut down

from 8:00 am -12:30 pm. Allen hall will be on Standby power during this time.

  • From 12:30 pm to 6:00 pm Allen hall will be on normal power without Standby backup.

Services Impacted:  The entire building will be affected.

Work Performed By:  Utilities and Energy and Contractor

ContactRick Tabor, CPFM Interim Co-Dir Utilities & Energy, 541-346-7511

To view current construction and impacts, visit UO Map.