Update 2/20/2020: The roof cleaning has been extended for the Alder Building, Straub, and the Indoor Tennis Courts. The work will be completed on Friday, February 28th.
Update 2/6/2020: Due to leaks that have appeared from the recent rains, this work has been delayed and is now expected to be completed on Friday, February 21st.
Update 1/21/2020: The roof cleaning has been extended for Villard, Computing Center, UO Annex, Hendricks, Gerlinger, Gerlinger Annex, Susan Campbell, Knight Library, Lokey ED, Clinical Services, Indoor Tennis Courts, and the Museum of Natural and Cultural History. The roof cleaning is expected to be completed on Thursday, February 6th.
Begin: December 23, 2019
End: January 23 February 21 28, 2020
Scope: Roof cleaning will be conducted across campus with the assistance of a lift. Please be aware of the lift staging area, which will move from building to building. Blowers may be utilized, but will not push the debris from the roofs. Some noise can be expected with this activity.
Special Instructions: Work will be performed during this window of time and specific dates are not being assigned to each building, but will be done in the order listed.
Contact: Work Control Center
Campus Roof Cleaning Schedule in Sequential Order:
Building |
Willamette |
Cascade |
Cascade Annex East |
Pacific |
Lawrence |
Allen Hall |
Friendly |
Fenton |
Villard |
Miller Theater |
McKenzie |
Computing Center |
UO Annex |
Chiles |
Peterson |
Lillis |
Condon |
Chapman |
Johnson |
Collier |
Hendricks |
Gerlinger |
Gerlinger Annex |
Susan Campbell |
Knight Library |
Alder |
Lokey Ed (Bldg 007) |
Lokey Ed (Bldg 041) |
Clinical Services |
Indoor Tennis Courts |
Esslinger |
SRC |
Straub |
Agate |
Vivian Olum |
MNCH |