UPDATE:
The concrete was poured today and will be drying over the weekend. It is currently sectioned off to prevent accidental use.
The contractor will be back on Monday to remove the forms, opening it back up to pedestrian and bicycle traffic. However, the concrete needs to continue to cure until next Friday, Sept. 20th, before vehicle/cart traffic will be able to use it. Signage will be posted on Monday to this effect.
Begin: Monday, September 9, 2024
End: Friday, September 13 20, 2024
Building(s) or Area(s) Affected: Sidewalk directly east of Lokey Education
Scope: Delta Sand & Gravel will be replacing the sidewalk on the east side of Lokey Education (see schedule below).
Monday 9/9 – cut concrete
Tuesday 9/10 – remove cut panels
Wednesday 9/11 – create forms
Thursday 9/12 – create forms
Friday 9/13 – pour new concrete
Services Impacted: The sidewalk will be unavailable during this time.
Special Instructions: Please use on using a different route.
Work Performed By: Delta Sand & Gravel
Contact: Work Control Center, Campus Planning and Facilities Management, 541-346-2319
Current construction and impacts information can be found on the UO Maps site.