UPDATE:
Renovations and remodeling are still in process and the end date has been extended into the middle of May.
Begin: Friday, January 12, 2024, at 8:00 am
End: March 31 Friday, May 17, 2024, at 4:00 pm
Building(s) or Area(s) Affected: Willamette Hall room 154
Scope: Room 154 will undergo renovation and remodeling.
Services Impacted: Contractors will be present in the building and lobby plus noise and odor can be expected with this type of work.
Work Performed By: Bridgeway Contracting
Contact: Waymon Banks, CPFM Owner’s Representative, 541-346-0196