Begin: Tuesday, January 3rd, 2023
End: Friday, January 20th, 2023
Building(s) or Area(s) Affected: Knight Library Room 57
Scope: Renovation work is being done in room 57. A flexible fresh air duct will be run down hall H57 and out the window of room 19 for two days only, January 4th and 5th. This may cause some ADA access issues. Paint, carpet and other refresh work will follow in room 57
Services Impacted:
- Access may be affected in Hallway H057 on Wednesday, January 4th, and Thursday, January 5th.
- Construction noise and odor can be expected in the area.
Work Performed By: PMG Demolition and CPFM Facilities Services
Contact: Janell Cottam, CPFM Owner’s Representative, 541-346-7536
Current construction and impacts information can be found on the UO Maps site.