Begin: Tuesday, December 6th, 2022, at 8:00 am
End: Tuesday, December 6th, 2022, at 4:00 pm or sooner
Building(s) or Area(s) Affected: Baker Downtown Center
Scope: Anderson Roofing will be installing a roof hatch on the south end of the building. This is the final activity for the Baker Roof Replacement project.
Services Impacted:
- The work will cause some noise but there should be no other inconveniences for the building occupants.
- A lift will be used to load materials and may block the alley for no more than 15 minutes.
Work Performed By: Anderson Roofing
Contact: Luke Helm, CPFM Owner’s Representative, 541-346-8216 or 458-256-7622