Oregon Hall Service Elevator Sump Pump Cleaning 2/13/2020

UPDATE: This shutdown needs to be extended until 4:00 pm today due to an unforeseen issue with the sump pump function that needs repair.

 

Begin:  Thursday, February 13th, 2020 at 7:00 am

End:      Thursday, February 13th, 2020 at 12:00 noon 4:00 pm

Building Impacted:  Oregon Hall

Scope:  Service elevator will be shut down to inspect and clean sump pit pump

Services Impacted:  Service elevator

Extra Notes:  Work will be performed by Preferred Construction

ContactBruce Budzik, Small Projects & Cap Imp Manager, 541-346-8834

Johnson Hall Building-Wide Water Shutdown 2/21/2020

Update 2/25/2020: The repairs were not able to be completed on Friday, February 21st, so the remainder of the repairs will be made tomorrow, February 26th.

Begin: Friday, February 21, 2020 at 7:00 pm Wednesday, February 26, 2020 at 7:00 pm

End: Friday, February 21, 2020 at midnight Wednesday, February 26, 2020 at 10:00 pm

Building Impacted: Johnson Hall

Scope: The plumbing issue affecting the Garden Level bathroom has been identified. A building-wide water shutdown must be enacted to make repairs.

Services Impacted: All water sources

Extra Notes: Do not use any water in the building after 7:00 pm.

Contact: Ken Straw at 541-346-5406 or kstraw@uoregon.edu