4/7: [OREGON HALL] Electrical Gear Outage Impacting Various Building Equipment & Areas 1E, 2E, 3E, 4E (all east wing areas)

This notice has been sent to all UO Spaces building contacts in Oregon Hall and Outlook Lists FS Memo and Computing Centers.

Building Occupants,

On Saturday, April 7, 2018, from 6:00 am – 3:30 pm Fortis Construction and JKG Electrical will be shutting down the basement electrical gear impacting the flowing equipment;

Freight Elevator
Passenger Elevators
Panel MSP1, west basement, basement pumps- chilled water/ heating/ condensate
Panel WRB, west basement, sump pump SP-3, exhaust fan EF-3
Water Heater in main basement
Panel ERB, main basement, hot water pump, sump pump SP4, dry pipe air compressor

Impacted Areas: 1E, 2E, 3E, 4E (all east wing areas)

Fortis will provide power to the air compressor and monitor the sump pumps.  This shutdown should not affect the data center.

For questions for concerns, please contact CPFM Design and Construction Owners Representative Patrick Mucker at 541-346-8216.