Begin: Monday, December 1, 2025, at 7:00 am
End: Friday, December 1, 2028
Building(s) or Area(s) Affected: Centennial Hall, Mary Neils Hall, Elizabeth Hall, Weber Hall, 6441 NE 30th House, parking at NE 29th Ave. between Centennial and Holman Apts, and the East Hall’s elevator.
Scope: Site preparation will begin for the new Child Behavioral Health Building. Beginning Monday, 12/1, the fencing will be installed. On the following Monday, 12/8, abatement will begin on all the structures within the fenced perimeter. Demolition to follow abatement in Spring/ Summer of ’26. East Hall elevator to be without phone service throughout the duration. Contact facilities if you need to operate the elevator. Updates will be sent out as the project progresses. The Child Behavioral Health Building construction is expected to be complete in the Winter ’28/29.
Services Impacted:
- No parking or pedestrian traffic within fencing perimeter.
- Abatement activities mostly limited to the interior of buildings and should not affect noise levels in surrounding areas.
- Vehicular / construction traffic to be expected.
Special Instructions: Alternate parking is available in campus parking lots or any of the side streets, except for NE 28th Ave..
Work Performed By: GC Skanska, Abatement by Rose City, Alpha, and PMG
Contact: Annie Karel, CPFM D&C Owner’s Representative, 541-346-8215
Current construction and impacts information can be found on the UO Maps site.