3/13/24 – 4/05/24 Huestis Hall Exterior Work and Move-In Advisory

Begin:  Wednesday, March 13, 2024

End:      Friday, April 5, 2024

Building(s) or Area(s) Affected:  Huestis Hall and surrounding area

Scope:  The Huestis Hall Deferred Maintenance Project is nearing final completion and the following is a list of upcoming work and impacts around the building:

  • March 13 – Mulching around the south and east
  • March 21 – Construction fencing will be removed on the south and east sides of Huestis Hall.
  • March 22 – April 5 – Construction fencing will remain in place around the Streisinger courtyard to allow for the following site activities:
    • The Coast Redwood tree removal. The growth habit of this tree species in the location poses a risk to infrastructure, property, and life.
    • Replanting, mulching, and landscape repairs in the courtyard and west walkway between Huestis and Willamette Halls.
  • March 25 – Construction trailer will be removed from the site on E. 13th Ave.
  • April 1 – 30 – Occupant move in activities
  • May TBD – Exterior art work installation on the exterior brick of the south stair tower

I appreciate the patience and collaboration from all of our campus partners over the last 2 years! Thank you!!

Services Impacted:  This will affect parking, roadways, and sidewalks in the area.  Noise can also be expected from the activities listed above.

Work Performed By:  Lease Crutcher Lewis and Rexius

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880