Begin: Wednesday, March 13, 2024
End: Friday, April 5, 2024
Building(s) or Area(s) Affected: Huestis Hall and surrounding area
Scope: The Huestis Hall Deferred Maintenance Project is nearing final completion and the following is a list of upcoming work and impacts around the building:
- March 13 – Mulching around the south and east
- March 21 – Construction fencing will be removed on the south and east sides of Huestis Hall.
- March 22 – April 5 – Construction fencing will remain in place around the Streisinger courtyard to allow for the following site activities:
- The Coast Redwood tree removal. The growth habit of this tree species in the location poses a risk to infrastructure, property, and life.
- Replanting, mulching, and landscape repairs in the courtyard and west walkway between Huestis and Willamette Halls.
- March 25 – Construction trailer will be removed from the site on E. 13th Ave.
- April 1 – 30 – Occupant move in activities
- May TBD – Exterior art work installation on the exterior brick of the south stair tower
I appreciate the patience and collaboration from all of our campus partners over the last 2 years! Thank you!!
Services Impacted: This will affect parking, roadways, and sidewalks in the area. Noise can also be expected from the activities listed above.
Work Performed By: Lease Crutcher Lewis and Rexius
Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880
Current construction and impacts information can be found on the UO Maps site.