9/21/23 – 4/30/25 Villard Hall and University Hall “Heritage Project” Fencing and Pathway Advisory

UPDATE:
Revised pedestrian route attached.

Revised pedestrian map 9-20-23

UO Heritage Pedestrian Routes 9.20.23

 

Begin:  Thursday, September 21, 2023

End:      Wednesday, April 30, 2025

Building(s) or Area(s) Affected:  Areas surrounding Villard, University, Lillis, Lawrence, Friendly, and Fenton Halls

Scope:  Due to the renovation of Villard Hall and University Hall, known as the “Heritage Project”, the site around both buildings will fenced off for the duration of the project.

Services Impacted:

  • This will affect the walking routes in the vicinity.
  • Temporary mulch paths with fencing will be installed, and remain for the duration of the project.
  • Walkways are anticipated to be reopened during the Spring of 2025.

Work Performed By:  Fortis Construction

Contacts: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Gene Mowery, CPFM Owner’s Representative, 541-346-5593

Current construction and impacts information can be found on the UO Maps site.

Image of Heritage Project Fencing Advisory Map 9-21-23 thru 4-30-25

Pages from Site Logistics Plan_Heritage_Phase 3 Rev2 SW Closed