Huestis, Lokey Labs, Streisinger, and Streisinger Loading Dock Construction Activity Advisory 1/20/22 – 1/22/22

Begin:  Thursday, January 20th, 2022

End:      Saturday, January 22nd, 2022

Building(s) or Area(s) Impacted:  Huestis Hall Suite 34

Scope:  Contractors will be drilling into the existing concrete slab on Thursday and Friday. Noise and vibration can be expected in the surrounding area. New concrete will be poured in the unoccupied basement space on Saturday with trucks staged at the Streisinger Loading Dock.

Services Impacted:

Thursday and Friday:   Noise and vibration in the surrounding areas.

Saturday:   1) Access to the loading dock will be blocked by trucks.

2) The Huestis Elevator will have limited service availability.

Work Performed By:  Mortenson Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880