UPDATE 5/17/21:
The HVAC system will be shut down while the ground floor level duct dampers are tested on Thursday, May 20th, between 7:00 and 8:00 am.
Original Notice
Begin: Monday, May 17, 2021
End: Friday, May 28, 2021
Building Impacted: McKenzie Hall
Scope: Replace existing storefront exterior entries at 6 locations on the main and ground levels. Each location is expected to take 2 days to replace.
Services Impacted:
- No additional electrical or HVAC disruptions are known at this time. A shutdown notice will be issued as necessary.
- Building access will be maintained during construction but may require detours. The contractor will post signs as necessary.
- Users can expect to hear construction noises like hammering, drilling, grinding, and see construction personnel and UO staff entering and exiting the building during normal business hours, but also as early as 6
Work performed by: Ryan Thomas Construction, Culver Glass, and CPFM Facilities Construction Services.
Contact: Theo Davis, CPFM Design & Construction Project Manager, 541-346-1012