Pacific Hall Emergency HVAC Shutdown 9/23/20

UPDATE:

The Firmware updates have been complete.

All systems are back to normal operations.

 

Begin:  Wednesday, September 23rd, 2020 at 7:00 am

End:      Wednesday, September 23rd, 2020 at 8:00 am

Building(s) or Area(s) Impacted:  Pacific Hall

Scope:  A necessary BAS System Firmware Flash is required to resolve MSTP communications issues on the BAS System.  This Firmware update will require a re-start of the BAS panel processor and result in all HVAC equipment being off line during the Firmware upload and system re-start.  The entire process should take less than 1 hour.

Services Impacted:  This emergency HVAC shutdown will affect the entire building’s cooling, exhaust, fume hoods, and HVAC air supply.

Special Instructions:  Please close all fume hood sashes the evening before, on Tuesday, September 22nd.

Work Performed By:   CPFM Facilities Services

ContactStacy Breaux, CPFM FS Building Automation Sys Field Supr, 541-521-5376