UPDATE 8/17/22: Work will continue for another six months.
UPDATE 5/3/22: The construction is not yet complete. Updated end date is now August 17th, 2022.
UPDATE 11/23/21:
The ZIRC project will be expanding their laydown area from November 29, 2021 through January 7, 2022 to include the spaces shown below in Lot 3B.
Please direct inquiries about ADA parking to James McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676.
Original Notice
Begin: Friday, July 2nd, 2021
End: Monday, May 2nd, 2022 August 17th, 2022 February 17th, 2023
Building(s) or Area(s) Impacted: Zebrafish International Resource Center (ZIRC)
Scope: Contractor mobilization for the ZIRC building addition will be starting soon.
Work Performed By: Fortis Construction
Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972