Notice: Pacific Hall Construction Impacts to Lab Gas, Drain Lines, Compressed Air, RO System and Water Starting 6/21/17 Ending 07/07/17

Building Occupants,

As part of the Pacific Hall Project, the following impacts will be happening starting June 21, 2017 and running through July 7, 2017.

 

Starting June 21, 2017, at 7:00 am

Ending June 22, 2017, by 4:00 pm

Scope: Lab gas will be disconnected temporarily to allow for construction activities.

 

Starting June 22, 2017, at 7:00 am

Ending June 23, 2017, by 4:00 pm

Scope: Lab sink drain lines need to be temporarily disconnected and configured to accommodate construction activities.

 

Starting June 23, 2017, at 7:00 am

Ending June 23, 2017, by 4:00 pm

Scope: Compressed air will be disconnected to allow construction activities.

 

Starting June 26, 2017, 7:00 am

Ending June 29, 2017, by 4:00 pm

Scope: RO water will temporarily be disconnected to allow for construction activities.

 

Starting July 5, 2017, at 7:00 am

Ending July 7, 2017, by 4:00 pm

Scope: The chilled and hot water will be temporarily disconnected to allow for construction activities.

 

For questions regarding these impacts contact CPFM Design and Construction Nick Pritchard at 612-803-0664 or Jen Miley at 541-346-1530.