11/01/23 Huestis Hall Basement Steam Shutdown

UPDATE:
This work has been rescheduled for Wednesday, November 1st as additional coordination was required to complete the piping installation for the new steam supply.

 

BeginOctober 25, Wednesday, November 1, 2023, at 5:00 am

End:      October 25, Wednesday, November 1, 2023, at 4:30 pm

Building(s) or Area(s) Affected:  Huestis Hall basement

Scope:  As part of the Huestis Renovation project, temporary steam source will be refed from the new permanent steam source.  This shutdown will remove the existing steam flow meter and tie into the new PRV station for the permanent steam supply.

Services Impacted:  This steam supply shutdown will take the following equipment offline in Huestis serving the Zebrafish facility and quarantine:

  • Exhaust Fans 1&2
  • AHU 1&2
  • Heat Exchange 1
  • Heating Water pump 1&2

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880