Begin: Tuesday, September 9, 2025, at 6:00 am
End: Friday, September 12, 2025, at 4:00 pm
Building(s) or Area(s) Affected: Portland Highland Hall
Scope: Highland Hall roof will be repaired on the east side.
Services Impacted:
- There may be noise impacts to occupants inside the building.
- Four parking spaces to the north and six parking spaces to the south will be used for construction equipment.
Work Performed By: Howard S Wright
Contact: Monika Hasek, CPFM Owner’s Representative, 503-412-3797
Current construction and impacts information can be found on the UO Maps site.