11/04/24 Hamilton Hall Electrical Vault Installation and Sidewalk Access Advisory

Begin:  Monday, November 4, 2024, at 7:00 am

End:      Monday, November 4, 2024, at 10:00 am

Building(s) or Area(s) Affected:  Area near Hamilton Hall

Scope:  To facilitate locating activities, towards the installation of a new electrical vault, the projects Contractor will be closing down a portion of sidewalk as shown in the included overview – please see alternate pedestrian path, shown in blue.

Services Impacted:

  • During this work, a vac-truck will be parked in the adjacent bike lane, also shown, with traffic controllers in place to assist with traffic movement. The adjacent crosswalk will remain open all through this activity.
  • Some construction noise will be present, intermittently.
  • The work area will be enclosed in construction fencing, for your protection. This fencing will remain in place until the vault is installed in December (scheduled to occur over winter break, weather depending).

Work Performed By:  EC Electric/Wildish

ContactDamon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285

Current construction and impacts information can be found on the UO Maps site.