8/07/24, 8/21/24, and 8/29/24 Huestis Hall and Lokey Labs Electrical Shutdowns

Dates Involved:         Wednesday, August 7, 2024, from 5:00 am to 7:00 am
Wednesday, August 21, 2024, from 6:00 am to 8:00 am
Thursday, August 29, 2024, from 6:00 am to 8:00 am

Building(s) or Area(s) Affected:  Huestis Hall, Lokey Labs

Scope:  To complete electrical coordination work between Huestis and Lokey Labs, three (3) separate electrical shutdowns are required as follows:

August 7, 2024, from 5:00 am – 7:00 am
– Lokey Labs: Brief 15-minute normal power shut down to Lokey Labs panel 2N5
– Huestis basement: 2-hour lighting outage in Huestis zebrafish facility 16A and 16B.

August 21, 2024, from 6:00 am – 8:00 am Standby Power
– Lokey Labs: Standby panel 2S2 will be offline. Kurt Langworthy to shut down servers prior to the event.
– Lokey Labs and Huestis Hall: Network will be down
– Huestis Hall: Siemens BAS will be affected by network disruptions, alarms are anticipated
– Huestis Basement: Standby power to Suite 34 will be offline.

August 29, 2024, from 6:00 am – 8:00 am
– Lokey Labs: Brief 15-minute standby and normal power shutdown to Lokey Labs panel 2N5.
– Lokey Labs: Siemens BAS will be affected, alarms are anticipated.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

Additional Instructions:  If you have concerns about accessing your workplace when elevator services are impacted, please contact your supervisor to find an appropriate accommodation.

Work Performed By:  EC Electric

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.