RESCHEDULED – UPDATE for Wednesday, August 28, 2024, at 7:00 am to Thursday, August 29, 2024, at 4:00 pm:
Due to rain in the forecast for Thursday 8/22 and Friday 8/23, the work near the air intake will need to be rescheduled to next Wednesday 8/28 and Thursday 8/29.
UPDATE for Thursday, August 22, 2024, at 7:00 am to Friday, August 23, 2024, at 4:00 pm:
On August 22 and 23 the contractor will be applying the liquid roof membrane near the air intakes that serve the third floor. To mitigate odor intrusion, the contractor has placed filters on the intakes, applied plastic covers over the platform, and will have industrial fans to divert the air away. Odor intrusion is likely throughout those two days and that it will be monitored by EHS.
UPDATE for Thursday, July 18, 2024, from 7:00 am to 7:15 am:
Lease Crutcher Lewis will shut down one roof top exhaust fan for 15 minutes. The EF3-1 affects restrooms and service rooms on the third floor: All Gender Restroom 311, Service 312B, Women’s Restroom 312, Electrical 354, Men’s Restroom 353
UPDATE for Tuesday, June 18, 2024, from 7:00 am – 4:00 pm:
As part of the re-roofing project the contractor will be pressure washing during this time, noise associated with this can be expected in the building and surrounding areas.
UPDATE 6/14/24:
- Interior stairs will only be used during the project’s first week 6/17 through 6/21. (There is no elevator in Klamath.)
- The contractor will begin prep work on the roof from 6/17 through 6/21.
- Construction for the reroofing project will begin on 6/24 and last 4-5 months.
- Scaffolding will be placed on the northeast corner of the building for the duration of the project.
- An indoor air quality management plan will be implemented to manage and monitor air quality in and around the site.
Begin: Monday, June 3, 2024 Monday, June 17, 2024, at 7:00 am
End: Friday, November 1, 2024, at 4:00 pm
Building(s) or Area(s) Affected: Klamath Hall, Lokey Laboratories, Price Science Commons, Streisinger Hall, Willamette Hall, Huestis Hall, Onyx Bridge, Cascade Hall, Lewis Integrative Science Building
Scope: A contractor will be re-roofing Klamath Hall.
Services Impacted:
- Elevator and The loading dock will be used temporarily throughout the project when needed. Further notice will be provided during those times.
- The project will have minimal noise and disruption.
- Some materials used may cause a harmless odor.
Work Performed By: Lease Crutcher Lewis
Contact: Waymon Banks, CPFM Owner’s Representative, 541-346-0196