Begin: Friday, February 2, 2024, at 6:00 am
End: Friday, February 2, 2024, at 8:00 am
Building(s) or Area(s) Affected: University Hall, Villard Hall, Miller Theatre Complex, Allen Hall, Lawrence Hall
Scope: Fire flow testing will take place at University Hall. This will be a short duration shutdown (under 1 hour) and won’t need the water valve shut off, but it will steal all of the water pressure supply of the other buildings mentioned, when they are performing the flow test.
Services Impacted: Water to entire buildings (listed above) will have reduced flow for a short period of time.
Work Performed By: Fortis Construction/Alliant Systems
Contact: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214
Current construction and impacts information can be found on the UO Maps site.