12/18/23 – 1/12/24 Knight Library Hallways H116 and H148 Construction and Access Advisory

Begin:  Monday, December 18, 2023, at 7:30 am

End:      Friday, January 12, 2024, at 4:00 pm

Building(s) or Area(s) Affected:  Knight Library hallways H116 and H148

Scope:  A contractor will be doing demolition and construction in hallways H116 and H148. They are replacing the four display cabinets in these halls. These are the two main North South passageways from the entrance to the body of the library.

Services Impacted:  There may be a temporary re-route from one hallway to the other during the demolition process.

Special Instructions:  Please watch for signage.

Work Performed By:  Richards Remodeling

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

Image of Knight Library Hallways H116 and H148