11/28/23 Huestis Hall Basement Heat Exchangers Shutdown

UPDATE 11/09/23:
The heating water system shutdown has been rescheduled for Tuesday, November 28th.   This was due to the upcoming steam shutdown on November 30th, and needing to do this work in sequence.

 

BeginNovember 9, Tuesday, November 28, 2023, at 6:00 am

End:      November 9, Tuesday, November 28, 2023, at 3:30 pm

Building(s) or Area(s) Affected:  Huestis Hall basement

Scope:  Huestis basement heat exchangers will be offline to allow contractors to tie the new heating loop from HX2 and 3 into the existing heating water loop for HX1.

Services Impacted:  This will require the exhaust fans, AHUs, heat exchanger 1, and heating water pumps 1 & 2 serving the Huestis basement to be shut down.

Work Performed By:  JH Kelly

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Image of Huestis Hall