Begin:  Monday, May 8, 2023, at 8:00 am

End:      Saturday, July 15, 2023, at 5:00 pm

Building(s) or Area(s) Affected:  Walton Project Area / Powell Plaza

Scope:  On May 8th at the Walton replacement project, we will shifting the fence line on Powell Plaza to the south in order to finish the landscaping on the project.

Services Impacted:  This will not impact pedestrian flow, and the fencing will remain in place until the removal of the fencing July 15th.

Special Instructions:  We will have a bump out in the fence to allow for deliveries.  During large track events, this bump out will be pulled back.

Work Performed By:  Fortis Construction

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

Current construction and impacts information can be found on the UO Maps site.