Begin: Monday, May 8, 2023, at 8:00 am
End: Saturday, July 15, 2023, at 5:00 pm
Building(s) or Area(s) Affected: Walton Project Area / Powell Plaza
Scope: On May 8th at the Walton replacement project, we will shifting the fence line on Powell Plaza to the south in order to finish the landscaping on the project.
Services Impacted: This will not impact pedestrian flow, and the fencing will remain in place until the removal of the fencing July 15th.
Special Instructions: We will have a bump out in the fence to allow for deliveries. During large track events, this bump out will be pulled back.
Work Performed By: Fortis Construction
Contact: George Bleekman, CPFM Owner’s Representative, 541-346-2625
Current construction and impacts information can be found on the UO Maps site.