UPDATE 4/26/23:
We will be blocking four spaces at the base of each of the two poles in Parking Lot 2 for the installation of the security cameras. This will occur Tuesday, May 2nd – Thursday, May 4th. We do not anticipate any other disruption to the area. Work will be performed by ADT Security.
UPDATE 3/30/23:
A crane truck will be in Parking Lot 2 tomorrow, March 31st, starting at 11:00 am to install the two light poles and heads. Spaces near the pole bases will be blocked tonight after work. The north access lane of the parking lot will be blocked for through traffic during the installation. If you park in this area, be aware you may be blocked during the time of the lift. Parking along the mill race and that access area will remain open.
UPDATE 3/07/23:
We will be closing spaces and blocking through traffic in Parking Lot 2, south of the CPFM building. User’s with B-North Permits are allowed to also park in C lots which include the Millrace Garage. Fencing will be up around the construction area. Be aware of construction equipment and activity when driving and parking in the remaining spots. The drive through area adjacent to the CPFM building will be re-opened between construction activities as possible. The drive through in the lot will be closed for the duration. The majority of the work and space closures will be completed by Monday, March 27. Additional camera installation and cabling will continue through March 31st. During the week of March 27th-31st, traffic lanes will be open and only a few spots near the new poles will be blocked for work.
UPDATE 2/7/23:
Parking spaces (approx. 35 spaces) and traffic flow in Parking Lot 2 will be impacted during the installation of two light poles with cameras.
We have moved the start date up by three days (3/20/23 – 3/31/23) so that the construction will be completed by the end of Spring Break.
We will coordinate with those using the lot for alternative parking solutions during the construction.
See revised diagram.
Begin: Thursday, March 23, 2023 Monday, March 20, 2023
End: Friday, April 07, 2023 Friday, March 31, 2023
Building(s) or Area(s) Affected: Parking Lot 2 (South of CPFM Warehouse)
Scope: Two new light poles with security cameras are scheduled to be installed in Parking Lot 2.
Services Impacted:
- This will impact the availability of some parking spaces and modify the traffic flow during the construction.
- Construction and Design is working with Parking to develop temporary parking solutions as needed.
Work Performed By: Preferred Construction
Contact: Janell Cottam, CPFM Owner’s Representative, 541-346-7536
Current construction and impacts information can be found on the UO Maps site.