Walton Hall Tower Crane Advisory 2/1/22 – 2/3/22

Begin:  Tuesday, February 1st, 2022 at 9:00 am

End:      Thursday, February 3rd, 2022 at 5:00 pm

Building(s) or Area(s) Impacted:  Walton Project Site at Agate and E. 15th Ave.

Scope:  We will be mobilizing and erecting a tower crane on the Walton Project site. This work will include a 600 ton helper crane. All activity will take place within the project fencing (no street closures), but be aware that there will be very large vehicles entering and leaving the site during this time

Services Impacted:  There will be no street closures, but extra flaggers will be employed to escort trucks in and out of the site.

Work Performed By:  Fortis Construction

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625