Buildings North of ZIRC Steam Heat Shutdown 11/01/21

UPDATE 11/1 at 3:26 PM: Steam has been temporarily restored. Further investigation and steam shutdowns will be required to permanently resolve the problem, but notifications will be sent out.

UPDATE 11/1: The steam pipe repairs are more extensive than originally anticipated. Steam heat will be down to the buildings north of ZIRC, including the greenhouses, for an unknown amount of time. An update will be sent when the steam is restored.

UPDATE 11/1: The water was restored and the restrooms are back online.

UPDATE 11/1: Due to an unforeseen issue with the steam pipe, the domestic water to Building 136 will be off for an unknown amount of time. An update will be sent out as soon as we find out more. The water is still on at Building 130 so please use the bathrooms there.

Begin: Monday, November 1st, 2021 at 8:00 am

End: Monday, November 1st, 2021 at 3:26 pm

Building(s) or Area(s) Impacted: CPFM Administration Quonset, FS Lock and Key Shop, MNCH Archaeological Research Lab, Paleoecology Research, Archaeology Research, MNCH Prep Lab, Quonset 108, and Greenhouses

Scope: The domestic water will be shut down for approximately one hour to repair a pipe damaged during construction work.

Services Impacted: The domestic hot and cold water will be offline.

Special Instructions: Please use the sinks and restrooms in nearby buildings during this time.

Work Performed By: Fortis Construction

Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972