13th Ave. & University St. – Sidewalk Core Drilling 8/30/21

Begin:  Monday, August 30th, 2021 at 12:00 noon

End:     Monday, August 30th, 2021 at 3:00 pm

Building(s) or Area(s) Impacted:  Sidewalk at 13th Avenue and University Street

Scope:  A valve box will be inset into the sidewalk, which will involve core drilling into the concrete.  The process should take approximately two to three hours.

Services Impacted:  Traffic will not be affected.

Work Performed By:  NW Natural Gas

ContactJames McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676