Hayward Field Feeder 1 Shutdown 7/18/20

Begin:  Saturday, July 18th, 2020 at 7:00 am

End:      Saturday, July 18th, 2020 at 3:30 pm

Building(s) or Area(s) Impacted:  Hayward Field

Scope:  Feeder 1, at the 6 way switch at Hayward Field, will be shut down in order to complete some additional work on the panels/transformers.

Services Impacted:  This Saturday shutdown should only affect the power at Hayward Field.

Additional Notes:  Standby 1 in  @ Vault 302 switch will be down intermittently.

Work Performed By:  Hoffman Construction and CPFM

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Chapman and Condon Steam Shutdown 7/17/20

Begin:  Friday, July 17th, 2020 at 7:00 am

End:      Friday, July 17th, 2020 at 3:00 pm

Building(s) or Area(s) Impacted:  Chapman Hall and Condon Hall

Scope:  Due to a failed valve in the utility tunnel, the steam to both Chapman and Condon will be shut down for 8 hours to replace the valve.

Services Impacted:  The building heat and the domestic hot water will be shut off during this time.

Work Performed By:  CPFM Utilities and Energy

ContactWork Control Center, Campus Planning and Facilities Management, 346-2319