Building Occupants,
As part of the Pacific Hall Project, the following impacts will be happening starting June 21, 2017 and running through July 7, 2017.
Starting June 21, 2017, at 7:00 am
Ending June 22, 2017, by 4:00 pm
Scope: Lab gas will be disconnected temporarily to allow for construction activities.
Starting June 22, 2017, at 7:00 am
Ending June 23, 2017, by 4:00 pm
Scope: Lab sink drain lines need to be temporarily disconnected and configured to accommodate construction activities.
Starting June 23, 2017, at 7:00 am
Ending June 23, 2017, by 4:00 pm
Scope: Compressed air will be disconnected to allow construction activities.
Starting June 26, 2017, 7:00 am
Ending June 29, 2017, by 4:00 pm
Scope: RO water will temporarily be disconnected to allow for construction activities.
Starting July 5, 2017, at 7:00 am
Ending July 7, 2017, by 4:00 pm
Scope: The chilled and hot water will be temporarily disconnected to allow for construction activities.
For questions regarding these impacts contact CPFM Design and Construction Nick Pritchard at 612-803-0664 or Jen Miley at 541-346-1530.