UPDATE 7/5: This project has been extended to July 29th due to the longer rainy season this spring.
Begin: Monday, April 25th, 2022
End: Thursday, June 30th, July 29th, 2022
Building(s) or Area(s) Impacted: Baker Downtown Center
Scope: The project to remove and replace the roof system at the Baker Downtown Center will begin on Monday, 4-25. Parking and access will be affected but adequate parking and access will be maintained at all times. The project is expected to be complete in late June.
Services Impacted: Parking and access on the exterior of the building.
Work Performed By: Anderson Roofing
Contact: Luke Helm, CPFM Owner’s Representative, 541-346-8216